The latest news on Te Kaha, Canterbury's Multi-Use Arena.

Weekly site progress

Monday 24 June 2024.

Above is a view of Te Kaha taken today.

The radial trusses are seen in the centre of the image, stretching around perimeter of the arena. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. 16 of the 40 total radial trusses are now in place.

Four radial diaphragm modules (RDMs) have also been installed. These steel structures attach to the tops of the radial trusses and will support the roof. These 60 tonne steel structures can be seen in the centre of the image above extending over the bowl of the arena. 

Te Kaha will be a completely covered arena, with part of the roof made of a clear material called Ethylene Tetrafluoroethylene (ETFE). The ETFE will let sunlight shine through from the north to support turf growth, while protecting visitors from the elements. This work will continue throughout 2024.

The image also shows the west stand in the foreground. This four-storey stand contains function spaces, player facilities, corporate boxes, and the coaches and media facilities. With the roof now completed in this stand, work continues on the fit-out, steelwork and painting. 

The seating plat installation in the upper bowl is almost complete and work on the plats in the lower tiers has started. In total, there will be 1663 seating plats in the arena. 1075 of these are in now place.

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Watch: Te Kaha roof a step closer

Friday 21 June 2024.

Take a look at the new drone flyover video from Te Kaha, Canterbury’s Multi-Use Arena.

BESIX Watpac’s Project Director Adrian Jones provides an update on how work is progressing on the $683 million construction project.

 “All of the seating plats are now installed in the western stand. The lower bowl seating in the east stand is just starting to form, which will take the seating all the way down to the field of play,” says Mr Jones.

Work on the arena roof and supporting structure is also progressing well, with the first two cantilever modules now installed. These 60 tonne steel structures extend over the bowl and will support the roof.

The roof components are being fabricated on site before being lifted by crane, and welded into place.

“We are preassembling all the large steel modules, being the radial perimeter columns and also the cantilever modules that hang out over the bowl structures. These modules will be installed progressively right through into early next year,” says Mr Jones.

Te Kaha will be a completely covered arena, with part of the roof made of a clear material called Ethylene Tetrafluoroethylene (ETFE). The ETFE will let sunlight shine through from the north to support turf growth, while protecting visitors from the elements. 

The project remains within budget, with Te Kaha on track to open in April 2026.

Past news and announcements

Weekly site progress

Monday 17 June 2024.

Above is a view of Te Kaha taken this morning.

The radial trusses are seen in the centre of the image, stretching around perimeter of the arena. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. 15 of the 40 total radial trusses are now in place.

The image also shows the west stand in the foreground. This four-storey stand contains function spaces, player facilities, corporate boxes, and the coaches and media facilities. With the roof now completed in this stand, work continues on the fit-out, steelwork and painting. 

The seating plat installation in the upper bowl is almost complete and work on the plats in the lower tiers has started. In total, there will be 1663 seating plats in the arena. Over 1000 of these are in now place.

Radial diaphragm modules (RDMs) have also started being installed. These steel structures attach to the tops of the radial trusses and will support the roof trusses. They can be seen in the centre of the image below, above the radial trusses. This work will continue throughout 2024.

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 11 June 2024.

Above is a view of Te Kaha taken this morning.

The radial trusses are seen in the centre of the image, stretching around perimeter of the arena. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. 15 of the 40 total radial trusses are now in place.

The image also shows the west stand in the foreground. This four-storey stand contains function spaces, player facilities, corporate boxes, and the coaches and media facilities. With the roof now completed in this stand, work continues on the fit-out, steelwork and painting. 

The seating plat installation in the upper bowl is almost complete and work on the plats in the lower tiers has started. In total, there will be 1663 seating plats in the arena. Over 1000 of these are in now place.

Radial diaphragm modules (RDMs) have also started being installed. These steel structures attach to the tops of the radial trusses and will support the roof trusses. They can be seen in the centre of the image below, above the radial trusses. This work will continue throughout 2024.

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Wednesday 5 June 2024.

Above is a view of Te Kaha taken yesterday.

The radial trusses are seen in the centre of the image, stretching around perimeter of the arena. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. 15 of the 40 total radial trusses are now in place.

Radial diaphragm modules (RDMs) have also started being installed. These steel structures attach to the tops of the radial trusses, and will support the roof trusses. They can be seen to the far right in the image below, above the radial trusses. This work will continue throughout 2024.

The image below shows the west stand in the foreground. This four-storey stand contains function spaces, the player facilities, corporate boxes, and the coaches’ and media facilities. With the roof now completed in this stand, work continues on the fit-out, steelwork and painting. 

The last few concrete seating plats for the upper bowl are being installed this week. The arena’s seats will be attached to the plats, which are supported by steel rakers. When finished, the arena will contain 1663 seating plats. Around 1000 of these are now in place, with the remaining plats set to be installed in the lower tiers once the upper tiers are complete.

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Monday 27 May 2024.

Above is a view of Te Kaha taken today.

The radial trusses are seen in the centre of the image, stretching around the south stand. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. We now have over a quarter of the radial trusses in place and are preparing to begin work on the roof structure. This work will continue throughout 2024.

The last few concrete seating plats for the upper bowl are being installed over the next few weeks. The arena’s seats will be attached to the plats, which are supported by steel rakers. When finished, the arena will contain 1663 seating plats. Around 1000 of these are now in place, with the remaining plats set to be installed in the lower tiers once the upper tiers are complete.

The roof of the west stand is now in place. This four-storey stand contains function spaces, the player facilities, corporate boxes, and the coaches’ and media facilities.  

The photo above was taken of the Te Kaha site from Tuam Street and shows the progress on the radial truss installations. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Faces of Te Kaha: Brian Hayes

Monday 27 May 2024.

Position: Project Director – Construction NZ 

Day to day... I work within a large team on the build side of the project. My job involves managing the team, forecasting ahead, and working on mitigation strategies for anything that comes up. 

The best part of my job: I always wanted to work in construction, so I’m really enjoying what I do. I like being with people and trying to get the best out of them. 

Past projects: I worked on the North Queensland Stadium, the home of the Cowboys. It’s great to work on a project that you can come back to and enjoy. I’ve also worked on some high-end residential developments on the river in Queensland. 

Outside of work... I like to keep fit with a bit of cross fit, a bit of mountain biking and keeping my kids occupied.  


Site progress

Wednesday 22 May 2024.

Above is a view of Te Kaha taken today.

The radial trusses are seen in the centre of the image, stretching around the south stand. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. We now have over a quarter of the radial trusses in place and are preparing to begin work on the roof structure. This work will continue throughout 2024.

The last few concrete seating plats for the upper bowl are being installed over the next few weeks. The arena’s seats will be attached to the plats, which are supported by steel rakers. When finished, the arena will contain 1663 seating plats. Around 1000 of these are now in place, with the remaining plats set to be installed in the lower tiers once the upper tiers are complete.

The roof of the west stand is now in place. This four-storey stand contains function spaces, the player facilities, corporate boxes, and the coaches’ and media facilities.  

The photo above was taken of the Te Kaha site from Tuam Street and shows the progress on the radial truss installations. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am. 

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Te Kaha construction hits halfway mark 

Tuesday 21 May 2024.

As the construction of Te Kaha, Canterbury’s Multi-Use Arena, reaches the halfway mark, Project Director Kent Summerfield shares an update from site.  

Over 700,000 workhours have gone into the construction project to date. Currently, around 300 contractors are working on site each day. 

The roof of the west stand is now in place. This four-storey stand contains function spaces, the player facilities, corporate boxes, and the coaches’ and media facilities.  

The steel framing in the northeast stand is now complete, and the concrete seating plats installation in this area are soon to be completed. The seating plats will support the arena’s tiered seating. 

When finished, the arena will contain 1663 seating plats. 923 of these are now in place, with the remaining plats set to be installed in the lower tiers in the coming weeks. 

The project remains within budget and on schedule to open in April 2026.  


Site progress

Monday 13 May 2024.

Here’s a view of Te Kaha taken today.

The radial trusses are seen in the centre of the image, stretching around the south stand. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. We now have over a quarter of the radial trusses in place and are preparing to begin work on the roof structure. This work will continue throughout 2024.

Work also continues this week on the concrete seating plats, which can be seen progressing around the bowl. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street and shows the progress on the radial truss installations. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Te Kaha snapshots

Tuesday 7 May 2024.

A quarter of the radial truss roof supports have now been installed.

The glass frontage of the function space, on level one of the west stand, is being installed. The space will be able to cater for around 900 guests.

The concrete seating plats now stretch about halfway around the east stand. The plats will support the arena’s seats.

Now that the plats in the south stand have been completed, aisle stairways are being installed.


Site progress

Monday 6 May 2024.

Here’s a view of Te Kaha taken today.

The radial trusses are seen in the centre of the image, stretching around the south stand. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. We now have over a quarter of the radial trusses in place and are preparing to begin work on the roof structure. This work will continue throughout 2024.

Work also continues this week on the concrete seating plats, which can be seen progressing around the bowl. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street and shows the progress on the radial truss installations. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Faces of Te Kaha: Phil Riding

Tuesday 30 April 2024.

Position: Services Site Manager

Day to day: I work with all services trades, like electricians and plumbers, to plan and programme in the work. There's a lot of forecasting and anticipating any issues that might come up and problem solving. 

The best part of my job is: the satisfaction of seeing progress from week to week, and being part of making it happen. 

Past projects: I've worked on the Court Theatre, a few schools, and the new workshop and office block for the Lyttelton straddle cranes.

Outside of work: I'm a volunteer firefighter for the Spencerville Volunteer Fire Brigade. We were involved in the response to the recent Port Hills fires. I was working 12 hour shifts, looking for any hotspots. It was great to have the support of BESIX to be able to go out and do this work. 


Watch: Behind the scenes at Te Kaha, Canterbury’s Multi-Use Arena

Monday 29 April 2024.

Take a look inside the west stand of Te Kaha, Canterbury’s Multi-Use Arena, in the latest video update. 

Project Director Kent Summerfield provides an overview of how construction is progressing on site. 

The concrete seating plats now stretch about halfway around the east stand. The plats will support the arena’s seats. 

A quarter of the radial truss roof supports have now been installed, with more being added each week, in preparation for the roof work beginning in the coming months. 

A lot of progress is also being made within the four-storey west stand, which houses player facilities, a function space, corporate boxes, coaches' and media facilities. The framing and glass frontage are being installed to the function space, along with a range of services. 

The project remains within budget and on track to open in April 2026. 


Site progress

Tuesday 23 April 2024.

Here’s a view of Te Kaha taken yesterday afternoon.

The radial trusses are seen in the centre of the image, stretching around the south stand. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. We now have a quarter of the radial trusses in place and are preparing to begin work on the roof structure. This work will continue throughout 2024.

Work also continues this week on the concrete seating plats, which can be seen progressing around the bowl. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street yesterday afternoon and shows the progress on the radial truss installations. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 16 April 2024.

Here’s a view of Te Kaha taken this morning.

The first radial trusses are seen in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. More radial trusses will be lifted into place this week. This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street this morning and shows the progress on the radial truss installations. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 9 April 2024.

Here’s a view of Te Kaha taken yesterday afternoon.

The first eight radial trusses are seen in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. More radial trusses will be lifted into place this week. This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street yesterday afternoon and shows the progress on the radial truss installations. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 2 April 2024.

Here’s a view of Te Kaha taken this morning.

The first eight radial trusses are seen in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. The seventh and eighth radial trusses were lifted into place this morning. Another two are scheduled to be installed on Friday, starting in the early morning at 3.30am (weather permitting). This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported by steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street this morning and shows the newest radial truss mid-installation. 

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 19 March 2024.

Here’s a view of Te Kaha taken this morning.

The first six radial trusses are seen behind the green crane in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. Two more radial trusses are scheduled to be installed on Saturday and Monday, starting in the early morning at 3.30am (weather permitting). This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported on steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Faces of Te Kaha: Jenny Divers

Monday 18 March 2024.

Position: Construction Survey Lead, Graham Surveying

Day to day: I'm in charge of all the survey work on site. Basically, we bring the designer's vision to life by building a full 3D model which shows where everything should go. The steel is manufactured to these specifications. Once it's built, my team also does quality assurance to make sure everything is right.

I've been on site right from the beginning of the project, working through the stages of piling, foundations, hold down bolts, and the bowl structure. We're now working on the roof stage.

The best part of my job is: Having the opportunity to work indoors and outdoors. I get a really nice mix of being on site and in the office with the team. It's also great getting to work with people from all different backgrounds and specialities. I've learnt so much about other trades and seeing how all the elements come together.

Past projects: I've worked all over Queensland doing construction surveying, including working on a new runway at Brisbane Airport, and high-rise residential buildings in Brisbane. 

Outside of work: I have a three-year-old daughter, so lots of time is spent on family trips to the beach or park. I'm also into smoking meat and craft beer, and we're in the middle of some home renovations. 


Watch: New update on Te Kaha

Friday 15 March 2024.

Take a bird’s eye view tour of Te Kaha, Canterbury’s Multi-Use Arena, as BESIX Watpac’s Project Director Adrian Jones provides an overview of how the $683 million project is progressing.


Site progress

Tuesday 12 March 2024.

Here’s a view of Te Kaha taken this morning.

The first four radial trusses are seen behind the green crane in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. Two more radial trusses are scheduled to be installed this week (weather permitting), from 3.30am on Friday and Saturday. This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported on steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Monday 4 March 2024.

Here’s a view of Te Kaha taken this morning.

The first four radial trusses are seen behind the green crane in the centre of the image. Due to their size, these steel roof supports are assembled on-site, before being lifted into place by crane. One more radial truss is scheduled to be installed this week (weather permitting), from 3.30am on Saturday. This work will continue throughout 2024.

From this vantage point, the concrete seating plats can be seen rounding the southwest corner. The arena’s seats will be attached to the plats, which are supported steel rakers. 

The photo above was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the east stand continues this week, heading towards the northeast lower bowl.

The precast concrete double tee floors continue to be installed, along with the installation of the tiered seating plats on the western and eastern stands. 

The assembly area for the radial truss roof supports is shown on the bottom left of the image. 

Over the coming months, trucks will continue to deliver oversized components of structural steel to the site. This will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site snapshot

Friday 1 March 2024.

Here are some still shots taken on site last month. 

Lifting one of the steel rakers into place. The rakers will hold the tiered seating.

Steel work for the lower bowl seating underway.

A look at the southern stand from within Te Kaha. The concrete seating plats are being installed around the southwest corner. The arena’s seats will be attached to the plats, which in turn are attached to the steel rakers.


Site progress

Monday 26 February 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the east stand continues this week, heading towards the north east lower bowl. The scale of the arena continues to develop as the bowl structure wraps around the arena. 

Works have also continued on the structural steel works for the west stand from levels 2 - 4, along with the pre-assembly of the roof. Installation of the radial truss roof supports has progressed and will continue over the coming months. The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Face of Te Kaha: Welcie Castalone

Wednesday 21 February 2024.

Position: Scaffolder, from Canterbury Scaffolding.

Day to day I: work to eliminate the risks of working at heights. We bring scaffolding equipment to the site and get it ready to install. Scaffolding is used to support the double tees before the concrete is put in.

The best part of my job is: getting together and working with my mates.

Past projects: I’ve worked in Punakaiki on a building site for a business. I’ve also worked at Fonterra inside drying plants working out how to set up scaffolding around all the machinery and piping, so that cleaning can take place. This was a pretty challenging job! 

Outside of work: I’m a drummer in a couple of bands, including a nu metal band and a wedding band. I’m also a car enthusiast and like working on my cars and going to car shows.  


Site progress

Wednesday 21 February 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the east stand continues this week, heading towards the north east lower bowl. The scale of the arena continues to develop as the bowl structure wraps around the arena. 

Works have also continued on the structural steel works for the west stand from levels 2 - 4, along with the pre-assembly of the roof. Installation of the radial truss roof supports has progressed and will continue over the coming months. The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 13 February 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the south stand continues this week, and will soon round the southeast corner to progress along the eastern stand. The scale of the arena is becoming clear as the upper bowl steelwork progresses. 

Works have also continued on the structural steel works for all stands, and for the pre-assembly of the roof. Installation of the radial truss roof supports has commenced. The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western, and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Video: February construction update

Thursday 8 February 2024.

Hear the latest from the Council’s project director Kent Summerfield as Te Kaha – Canterbury’s Multi-Use Arena hits a new construction milestone.

The western stand is now at full height, and the first of 40 radial trusses was installed just before Christmas, marking a new phase in the construction project.

Four more radial trusses are being built on site and will be lifted into place by crane in the coming weeks. The trusses are key pieces of structural support for the roof of the arena and work to build and install these will continue throughout 2024.


Site progress

Thursday 8 February 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the south stand continues this week, and will soon round the southeast corner to progress along the eastern stand. The scale of the arena is becoming clear as the upper bowl steelwork progresses. 

Works have also continued on the structural steel works for all stands, and for the pre-assembly of the roof. Installation of the radial truss roof supports has commenced. The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western, and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 30 January 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the south stand continues this week, and will soon round the southeast corner to progress along the eastern stand. The scale of the arena is becoming clear as the upper bowl steelwork progresses. 

Over the last week, works have also continued on the structural steel works for all stands, and for the pre-assembly of the roof. Pre-assembly of the roof and installation of the roof radial trusses has commenced(external link). The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western, and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Site progress

Tuesday 23 January 2024.

This photo was taken of the Te Kaha site from Tuam Street this morning.

Work on the upper bowl of the south stand continues this week, and will soon round the southeast corner to progress along the eastern stand. The scale of the arena is becoming clear as the upper bowl steelwork progresses. 

Over the last week, works have also continued on the structural steel works for all stands, and for the pre-assembly of the roof. Pre-assembly of the roof and installation of the roof radial trusses has commenced(external link). The assembly area can be seen on the far left of the picture above. 

The precast concrete double tee floors continue to be installed on the western, and eastern stands, along with the installation of the tiered seating plats on the southern and western stands. 

Over the coming months, trucks continue to deliver oversized components of structural steel to the site. These movements will be happening before 7am so that the oversized wide loads are off the road before the restrictions begin at 7am. Contractors will unload and lift the loads from 7am.

We expect to receive about two oversized deliveries a week. However, we are unable to provide specific times due to the susceptibility to work processes and weather conditions, such as priming and painting.


Looking for older news?

Check out the 'Newsline stories' or 'Newsletters' dropdown boxes for the full archive, or feel free to get in touch with the team by emailing info@tekahaproject.co.nz

Newsline stories

2024

2023

2022

2021

2020

2019

2018

Newsletters

Get the latest from Te Kaha - Canterbury's Multi-Use Arena

Sign up for monthly updates on the Te Kaha project as construction begins.

Sign up

2024

2023

2022

2021

2020