On Thursday 12 November 2020 the Council unanimously approved a $12.5 million package of works to reduce flooding and erosion in Southshore and South New Brighton.

Subscribe to the Coastal Futures newsletter

Also, check our Council Facebook page(external link) to stay in touch with what is happening.

The work approved by the Council includes:

  • Replacing or covering the structures along the estuary edge in Southshore to reduce the erosion risk.
  • Building a new bund in Southshore to reduce the flood risk.
  • Restoring the estuary edge in South New Brighton with a cobble beach.
  • Constructing a new bund away from the estuary edge within South New Brighton Park, between the jetty near Beatty Street and the southern end of the campground in Halsey Street.
     

Project updates

December 2022 update

To help people visualise what the Southshore residential red zone and estuary edge could look like once all the flood and erosion work is complete, we’ve created some artist's impressions [PDF, 1.9 MB].

These images are just indications  - they don’t show any particular street end, and the features such as parking and the entrances to the water are generic examples. As more detailed plans are developed, some aspects of the vegetation shown here may change. 

However, what they do show is how all the elements of the Southshore South New Brighton Estuary Edge Project - the flood and erosion work, and the recreation, cultural and ecological aspects - come together to create a really attractive asset for the community and the wider city

See the artist's impressions.

February 2022 update

With funding agreed in the Long Term Plan and Jacobs now on board to lead the technical work, we’re well into the preliminary design phase of the project.

During this stage, the project team is working out some of the key design elements, like the best location for the bund, how the different estuary edge treatments will tie in together, how to cover the existing rubble material that isn’t being removed, and how we can access the area while doing as little damage to the environment as possible.

At the same time, the Project Team is also pulling together the information we need for our resource consent. This includes coordinating with technical specialists to assess environmental, ecological, cultural and archaeological features of the site.

There are also some key partners, like Ngāi Tahu and Environment Canterbury, as well as directly affected properties that we will engage with as part of this process.

All things going to plan, we’ll be submitting our resource consent in July 2022. Given the complexities of this project, it could take up to a year for the consent to be assessed and approved, which means we won’t be starting the detailed design phase until July 2023.

If things move faster and the consent is processed more quickly, we’ll adjust this timing, but construction is currently planned to start early in 2024.

The consenting process

The Southshore Residents' Association asked the Project Team to investigate whether we could fast-track the consenting process for the estuary edge flooding and erosion mitigation works using the Government’s COVID-19 Recovery (Fast-track Consenting) Act. 

We had an initial chat with the staff at the Ministry for the Environment and they suggested that this project may be eligible. However, on balance, Jacobs and Council staff have decided that the Fast Track option isn't the best option for this project and that we should stick to the traditional Resource Management Act consenting process. 

The main reason for this is the scale of this project – as the legislation is designed to boost economic recovery during COVID-19, projects need to demonstrate significant economic benefit in order to be considered. Projects typically need to be nationally or regionally significant to qualify for this process.

While the Estuary Edge Project is important for the local community, it doesn’t significantly benefit the wider Canterbury region. Most projects that have been approved for the fast-track consenting process will create hundreds of jobs during construction and/or operation. You can find out more about the projects that have been successfully referred for fast-track consenting on the Ministry for the Environment website(external link).

Another key consideration is whether the fast-track consenting process would actually be any quicker for this project. The fast-track process takes longer to prepare but has a shorter processing time, whereas the traditional process has a shorter time to prepare but a longer time for processing. Overall, the time for preparing and lodging the consent is expected to be similar, regardless of the process. 

There are also some key advantages to the traditional RMA process - there is more opportunity and flexibility to respond to key stakeholder feedback as the process progresses, and it's less costly. 

We all agree that the Estuary Edge Project would positively contribute to many of the intended aims of the Fast-Track Consenting Act.  However, the threshold for acceptance is extremely high, there are no guarantees that we would be accepted into the process, and it's not necessarily any faster. For this project, we believe that proceeding with consenting through the RMA is the best option.

Traditional Resource Management Act process

Pros Cons
Greater ability to consider issues and respond to submitters through pre-hearing meetings. Estimated 12 months of processing time post-lodgement.
Flexibility to continue to work through certain aspects, such as cultural considerations, or incorporate suggested design changes from stakeholders post-lodgement. Right of third party appeals to the Environment Court and further opportunity for High Court appeals which could delay the project by up to 18 months.
Process well-understood by the project team.

 

The project team has more input on the conditions of the consent – allowing for greater flexibility in how effects are to be managed.  

 

Fast-track COVID-19 legislation

Pros Cons
The process from lodgement typically takes 6 to 7 months. No option to add new activities or consents post-lodgement which means more work and time upfront to complete all the technical assessments before lodgement.
Initial discussions with the Ministry for the Environment suggest that this project may be eligible. Having to complete everything upfront will also impact construction methodology – which will likely be more conservative, to avoid having to restart the consenting process for any changes.
There is no option to appeal the application to the Environment Court.  The fast-track process prescribes, and therefore limits, the parties to be consulted for the application. It also introduces groups such as Generation Zero, Greenpeace, Forest and Bird, and the Environmental Defense Society.
  More expensive process and uncertainty that the project will be accepted for the fast-track process.
  Delays are possible in appointing a Panel to decide on consent.

Project background

In May 2019 the Christchurch City Council took over leadership of South New Brighton and Southshore work that was previously led by Regenerate Christchurch as part of the Southshore South New Brighton Regeneration Strategy.

The work was split into two:

  1. Urgent investigations into earthquake legacy issues and repairs.
  2. A coastal hazards adaptation planning project, which is a longer-term conversation focused on how Christchurch adapts to coastal hazards in the short, medium and long term. Read more about this decision(external link).

The Earthquake Legacy Issues Project is about identifying outstanding community needs that have arisen from earthquake changes to the estuary edge in Southshore and South New Brighton and, where possible, developing responses to these needs.

On 29 August 2019 Christchurch City Council decided on responses to the earthquake legacy issues in South New Brighton and Southshore.

We're now in the process of implementing these decisions.

What we mean by earthquake legacy

Underpinning the Earthquake Legacy Issues Project is the acknowledgement that earthquake legacy issues have had, and continue to have, a significant impact on community wellbeing in Southshore and South New Brighton.

It was clear from community feedback we received that people felt very strongly about addressing earthquake legacy issues first, before starting a conversation about coastal hazard adaptation planning.

The purpose of the Earthquake Legacy Issues Project was to investigate and develop responses to earthquake-rated changes to the estuary edge in Southshore and South New Brighton.

Examples of earthquake legacy changes:

  • If it’s in relation to inundation (flooding), we mean changes in the level of service that was provided prior to the earthquakes. For example, the level of flood control that was in place.
  • If it’s in relation to erosion, we mean damage to existing structures as a result of the earthquakes.
  • If it’s about land damage from the earthquakes, we mean changes to land elevation and damage to land, such as lateral spread.
  • And if it’s about groundwater, we mean changes in groundwater levels.

Options to address earthquake legacy issues need to be practicable, feasible and not compromise the range of options available to the community when the Coastal Hazards Adaptation Strategy project begins.

For the Council, practicable and feasible would mean the best options for preventing or minimising the adverse effects on the environment and complying with the Council’s regulatory, operational, budgetary, and benefit/cost requirements.

The options also need to address outstanding community needs.

During May and June  2019 we worked with the South New Brighton and Southshore communities to identify a long list of community needs relating to earthquake changes to the estuary edge. We collated and themed the needs, and came up with some draft statements that were published for comment. With the help of some community representatives, and using the feedback we received, we then finalised the community needs.

These needs were used to help assess options to respond to the earthquake-related changes to the estuary edge.

Related documents:

Timeline

Council decision

9 May 2019

Council takes over leadership of work previously in scope of the Southshore and South New Brighton Regeneration Strategy.

Community needs workshop

29 May 2019

Workshop with community stakeholders and some residents to identify outstanding community needs that have arisen from earthquake-related changes to the estuary edge south of Bridge Street.

Community needs workshop

13 June 2019

Workshop with community stakeholders and some residents to identify outstanding community needs that have arisen from earthquake-related changes to the area north of Bridge Street.

Engagement with community

21 to 27 June 2019

Engagement on community needs.

Information gathering

June to July 2019

Technical reports commissioned to assess pre and post earthquake state of the estuary edge, looking at inundation, erosion, liquefaction and groundwater. 

Options and actions

June to July 2019

Existing and new options and actions identified and assessed to identify a shortlist of options. 

Community feedback

1 to 6 August 2019

Community feedback on options.

Council meeting

29 August 2019

Council meeting.

Council decision

9 May 2019

Council takes over leadership of work previously in scope of the Southshore and South New Brighton Regeneration Strategy.

Community needs workshop

29 May 2019

Workshop with community stakeholders and some residents to identify outstanding community needs that have arisen from earthquake-related changes to the estuary edge south of Bridge Street.

Community needs workshop

13 June 2019

Workshop with community stakeholders and some residents to identify outstanding community needs that have arisen from earthquake-related changes to the area north of Bridge Street.

Engagement with community

21 to 27 June 2019

Engagement on community needs.

Information gathering

June to July 2019

Technical reports commissioned to assess pre and post earthquake state of the estuary edge, looking at inundation, erosion, liquefaction and groundwater. 

Options and actions

June to July 2019

Existing and new options and actions identified and assessed to identify a shortlist of options. 

Community feedback

1 to 6 August 2019

Community feedback on options.

Council meeting

29 August 2019

Council meeting.

Southshore

Last project update - November 2020

On Thursday 12 November 2020 the Council unanimously approved a $12.5 million package of works to reduce flooding and erosion in Southshore and South New Brighton. 

The work approved by the Council includes:

  • Replacing or covering the structures along the estuary edge in Southshore to reduce the erosion risk.
  • Building a new bund in Southshore to reduce the flood risk.

Read more in the November 2020 Coastal Futures newsletter [PDF, 1.7 MB].

About the area

There have been changes to the estuary edge due to the land lifting in places, damage to some private protection structures, and some small areas where the land was lowered during clearance works.

Removal of residential red zoned properties along the estuary edge has left an area of open space which is largely being used for recreation and enjoyment but has not been enhanced or developed for this use.

Many of the private structures which provided varying levels of erosion and flood protection still provide a functional purpose in their current state. However, there are also sections that are unstable or have left exposed materials which create a health and safety risk.

There may be some increased risk to low lying properties on Rocking Horse Road adjoining the red zone due to changes to the estuary edge structures and the clearance of land where there used to be houses.

Any flood risk is largely managed through the bund which was constructed by Land Information New Zealand (LINZ) after the clearance works. Emergency works in July 2017 extended the bund across the road ends. There are some remaining low points in the LINZ bund on Crown land, otherwise, a consistent level of protection of RL 11.2m is provided.

There are pockets where increased erosion is occurring immediately behind private protection structures increasing the risk to residential red zone land and parts of the LINZ bund where this is close to the estuary edge.

Proposed options for the area

The proposed options to address flooding were:

These options address the following community need:

  • Protection from flooding from the estuary.

The proposed option to address erosion was:

This option addresses the following community needs:

  • Protect estuary edge from further erosion.
  • Repair of estuary-edge erosion protection, taking into consideration the protection that was previously afforded by structures that were privately owned.

Community feedback on the options and Council decision

In total, 141 residents provided feedback on the Southshore options and a large proportion of the community disagreed that either of the proposed flooding options met their needs. 

While 44% of respondents agreed that the proposed setback bund met their needs, 47% disagreed.  Only 31% agreed that improving the existing bund met their needs, while 59% disagree.

A higher proportion of respondents (66%) agreed that the proposed option to address erosion through an initial investigation met their needs, and 29% disagreed.

Sentiments raised at the Community Assessment drop-in, and reinforced by emails from the Southshore Residents Association and the Christchurch Coastal Residents United noted the following issues:

  • An engineered bund is sought, but not set back as proposed and instead located where the LINZ bund is currently positioned.
  • Erosion protection should be integrated with any proposed flooding solution.
  • Residents are seeking immediate solutions to erosion and flooding for now and into the future.  However, there is some appetite for Council to undertake further investigation and then provide the community with an integrated flooding and erosion proposal.

While the proposed bunds were an appropriate response to the increased flood risk created by earthquake legacy issues, Council staff recognised that these options may not sufficiently address the community's need for certainty and wellbeing. 

The recommended option included in the report to Council on 29 August 2019 was, therefore, Phase one: Investigate immediate and longer-term erosion options (including options for the edge structures) and advise on the position of the bund.

On 29 August 2019 Council decided to proceed with the following:

  • Requests staff to investigate immediate and longer-term erosion options in Southshore (including options for the privately-owned edge structures).
  • Requests that a collaborative group be established which includes a technical expert nominated by the Southshore community, to investigate the immediate Earthquake Legacy edge issues for the Estuary Edge repair and protection including the development of a suitable erosion mitigation plan with costings (including options for the formerly, privately-owned edge structures, and the position of the 11.4 m bund).
  • Notes the above Southshore Erosion Mitigation Plan will be presented in the first instance to the Southshore Residents Association and the Coastal-Burwood Community Board for comment before presentation to Council in early 2020.
  • Recommend that funding be made available for implementation of the estuary edge earthquake legacy repair in 2020 and urgently prioritised. 

South New Brighton – south of Bridge Street

Last project update - November 2020

Since August 2019 we have constructed the southern and northern sections of a bund in South New Brighton, between Bridge Street and South New Brighton School.  Work on the middle section of the bund will be completed in 2021 following the bird-nesting season.

For the estuary edge from the Yacht Club to the boardwalk, the August 2019 Council resolution was to restore using reno mattresses and gabion baskets as previously existed pre-earthquake.

We looked at both reno mattresses and a cobble beach approach to restoration. In the end, we determined the cobble beach was the preferred option and best met the intentions of the Council resolution. Both options would achieve pre-earthquake levels of erosion management, but the cobble beach is better because it:

  • Is easier to repair and maintain.
  • Has a shallower slope which reduces the potential for its base to erode.
  • Can be adapted for sea-level rise.
  • Enables easier to access the shoreline,
  • Creates a more naturalised edge
  • It will help restore the salt marsh in the area,
  • Is more consistent with the Council’s Biodiversity Strategy and the South New Brighton Reserves Development Plan.
  • Is more likely to be granted consent.

On Thursday 12 November 2020 the Council unanimously approved a $12.5 million package of works to reduce flooding and erosion in Southshore and South New Brighton. 

The work approved by the Council includes:

  • Restoring the estuary edge in South New Brighton with a cobble beach. 
  • Constructing a new bund away from the estuary edge within South New Brighton Park, between the jetty near Beatty Street and the southern end of the campground in Halsey Street.

Read more in the November 2020 Coastal Futures newsletter [PDF, 1.7 MB].

About the area

South New Brighton Park, between Beatty Street and the boardwalk, is the part of the Project Area that is the most affected by tidal flooding and erosion.

While this area experienced flooding and erosion before the earthquakes, the earthquakes have caused the land to drop in places, and some of the existing erosion protection structures have moved. This has led to further erosion and flooding of the edge.

The assets most at risk from these changes are the existing tracks and the Reserve land. However, there is also a potential increased risk of flooding to low-lying Estuary Road properties and the South New Brighton Holiday Park and Tennis Club.

There is little evidence of erosion north of Beatty Street, and the area is well planted. Land that has dropped along the estuary edge has potentially increased the flood risk to low-lying properties in Seafield Place and north of Bridge Street, but the level and extent of this risk have not been fully investigated.

The boardwalk in South New Brighton Park and adjacent embankments have been repaired to the pre-earthquake condition. South of the boardwalk to Caspian Street there are no obvious or outstanding earthquake legacy issues.

The Ebbtide Street stopbank and rock wall have been repaired to respond to earthquake damage and provide a consistent level of service as existed before the earthquakes.

Proposed options for the area

These options address the following community needs:

  • Protection from flooding from the estuary.
  • Protect the estuary edge from further erosion.
  • Protect the South New Brighton Park and Playground, South New Brighton School, South New Brighton Tennis Club, South Brighton Playcentre and the South Brighton Holiday Park from increased flood risk.

Community feedback on the options and Council decision

In total 110 residents provided feedback on these options with a preference for the set-back bund and sloping beach across all three questions asked. 

63% agreed or strongly agreed that this option responds to the earthquake legacy issues identified by the community, 66% agreed that this option would improve their quality of life, and 65% agreed that this option provided the community with a sense of confidence in their future.

However, a significant number of respondents also supported the option of a bund close to the edge with the repair of the existing protection structures (53% agreed or strongly agreed that this option responds to the earthquake legacy issues identified by the community). 

The recommended option included in the report to Council on 29 August 2019 was for new setback bunds with a range of hard and soft erosion management methods between Bridge Street and the boardwalk adjacent to the South New Brighton Park.

On 29 August 2019 Council decided to proceed with the following: 

  • For the Estuary Edge, Bridge Street to Jetty area, acknowledge the current salt marsh and implement engineered set back bunds giving protection to the South New Brighton School and Seafield Place.
  • For the Estuary Edge, Yacht Club to the boardwalk, implement restoration of the edge as per earthquake legacy edge repairs using reno mattresses and gabion baskets as previously existed pre-earthquake.
  • For staff to report separately on any flood protection measures that may be required for the area, in the context of this report.

South New Brighton – north of Bridge Street

Last  project update - July 2021

In response to Council resolution CNCL/2019/00196(external link), engineering consultancy GHD was commissioned to complete an updated risk assessment of the stopbank from Pages Road to Bridge Street.

The assessment found that the risk to life is low from the stopbank failing or being overtopped by water in 1 in 100-year annual recurrence interval events. The annual risk of one person dying as a result of a 1 in 100-year annual recurrence interval tide is less than 1 in 900,000.

Read the 2021 Ōtākaro Avon River stopbank assessment - Pages Road to Bridge Street. 

About the area

Land in this area dropped after the earthquakes, which has increased both the risk of flooding and the effects of shallow groundwater. 

While remediating earthquake-related land damage is the Earthquake Commission’s responsibility(external link) Council has mitigated the increased flood risk by raising and repairing stopbanks in this area.

The stopbanks are now at a level of RL 11.4m, which is higher than was provided before the earthquakes and consistent with, or higher than, other parts of the Ihutai/Estuary.

However, we know that if the river was to exceed the height of the stopbanks, the consequence to people and property is now greater. This is because the land is lower on the landward side of the stopbank, which increases the potential depth of floodwaters.

Proposed option for the area:

This option addresses the following community need:

  • Ensure that stopbanks are well-constructed and do their job of keeping people safe from flooding.

Community feedback on the option and Council decision

In total 45 residents provided feedback with 54% agreeing that this option responds to the earthquake legacy issues identified by the community. 

In their comments, people indicated that they wanted assurance that any remedial actions would be addressed, and they raised concerns that this work had not progressed more rapidly.

The option included in the report to the Council on 29 August 2019 was to undertake a stopbank condition assessment and an update of previous investigations into the life-safety risk of flooding from a breach or overtopping of the stopbanks between Pages Road and Bridge Street to account for the updated 2018 high tide statistics and to report the result of that investigation to the Council and the community.

On 29 August 2019 Council decided to request staff to undertake the assessment.

Areawide

In response to the community needs around recreation, access and enjoyment, we've proposed an option for this whole area:

Option: Continuous walkway/cycleway and enhanced recreation areas [PDF, 636 KB].

  • Provide a continuous walkway/cycleway adjacent to the estuary, with occasional setbacks where required, to ensure that it is safe and not prone to regular flooding.
  • Sections would be raised, repaired, finished, widened or rerouted.
  • Community-led enhancement of the Southshore red zone to include picnic tables, plantings, and spaces to learn about and observe nature.

This option provides a continuous walkway/cycleway along the Ihutai/Estuary, which is occasionally set back from the estuary edge, where required, to ensure that it is safe and not prone to regular flooding. It would enhance the red zone land in Southshore through the addition of picnic tables, native plantings, and spaces to learn about and observe nature.

We will raise, repair, finish, widen or reroute the existing walkway/cycleway from Evans Avenue right down to the south end of the red zone. In the future, this cycleway could link to the Te Ara Ōtākaro trail.

The track will be finished to the Council standard track design - 1.5m wide, 75mm base layer of compacted gravel, topped with 25mm crusher dust, with timber edge.

The enhancement of red zone land in Southshore could be community-led through the application for a transitional use lease from Land Information New Zealand (LINZ) and there are opportunities to apply to Council for community grants funding.

This option will be broken into smaller projects and staged so that some work could happen quickly.

What else we're doing to address community needs

Maintenance and levels of service

We’ve heard your concerns about how we maintain and care for the parks and public spaces in this area.

We’re reviewing our maintenance schedules to make sure this area is receiving the same level of service, and to the same standard as the rest of the city.

Recreation, access and enjoyment

The South New Brighton Reserves Development Plan(external link), which covers the four South New Brighton reserves has a whole programme of work around maintaining and enhancing the parks and reserves along the estuary edge, including some significant planting work.

We’re reviewing the Plan to make sure the timing of this work is prioritised and is well-coordinated with other work that may be happening in the area.

We also have an area-wide option for a continuous walkway/cycleway and enhanced recreation areas [PDF, 636 KB].

Stormwater management

There are no quick fixes to the stormwater issues in this area. Even before the earthquakes Southshore and South New Brighton were low lying areas that experienced issues with stormwater drainage.

Changes to the land from the earthquakes have only made this worse, as it has in other areas of the city. Read more about stormwater [PDF, 798 KB].

In the short term, we will be increasingly reliant on temporary pumping, as we are in other areas of the city, to manage stormwater.

We are reviewing our longer-term approach to stormwater management through existing Council programmes, and this is something that will be considered as part of adaptation planning for the area.