What |
We are replacing old water and sewer pipes. |
---|---|
Why |
The old pipes are worn and we need to install new ones to service the area now and into the future. |
Where |
Riccarton Road (between Matipo Street and Hansons Lane), Riccarton. |
When |
***DAY WORKS: 14 June 2021 to late March 2022. Monday to Friday, 7am to 6pm (weather/site condition dependent). |
Contact |
The contractor is Fulton Hogan. Phone 0800 762 334, Monday to Friday, 7am to 6pm. Access to properties will be restricted so please get in touch with us if you have conflicting priorities during work hours. |
We’re replacing old water and sewer pipes along Riccarton Road, between Matipo Street and Hansons Lane. The new pipes will more efficiently service the area into the future.
The project is split into three zones (refer to map) to allow us to complete the project as quickly as possible by working in each zone at the same time. We will progress the work in the same direction as the traffic.
Service location and preparation work (14 June to late June 2021, 7am and 6pm):
Water and sewer replacement (July 2021 to March 2022):
Night Works:
Service location and preparation work (14 June to late June 2021, 7am and 6pm): We'll begin service location work in each area. We will be digging small test holes to find services throughout the site.
East Zone (Matipo Street to Clyde Road): The new watermain will be located on the south side of the road, with upgrades to the sub main network within the footpaths. As we move west, the trench will be resurfaced and traffic lanes and parking reinstated.
Central Zone (Clyde Road to east of Ilam Road): The new watermain will be located on the north side of the road, with upgrades to the sub main network within the footpaths. As we move east, the trench will be resurfaced and traffic lanes and parking reinstated. There will be localised repairs to the existing sewer within this zone. The extent of this work will be communicated closer to the time.
West Zone (west of Ilam Road to Hansons Lane): The new watermain will be located on the north side of the road, with upgrades to the sub main network within the footpaths. As we move east, the trench will be resurfaced and traffic lanes and parking reinstated. There will be localised repairs to the existing sewer within this zone. The extent of this work will be communicated closer to the time.
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.