Taylors Mistake Road – new retaining wall

What

We will be constructing a new retaining wall to remediate a failing slope above the road.

Why

The works are necessary to improve the resilience of the road and surrounding land, making it safer for nearby residences and road users.

Where

Below 215 Taylors Mistake Road, 150m from the Taylors Mistake Surf Life Saving Club.

When

18 May 2026 to late June 2026. Monday to Friday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is Downer Ltd. Phone 021 379 023, Monday to Saturday, 7am to 6pm. Please talk to the contractor about any specific access requirements as soon as possible.

Details

The construction works will cause disruption to regular commuting through this section of road, with time frames highly weather dependant.

Traffic management will be in place and will change during the construction project. It will include a mix of traffic light one-way systems and daytime closures.

Planned Work

Construction of a new retaining wall: 18 May - end June

  • Excavation and clearance of the slope
  • Drilling and pouring of concrete for steel piles
  • Installation of precast concrete wall panels
  • Drainage installation and backfilling
  • Reinstatement works, including topsoil, hydroseeding, and planting

 Further updates with specific dates and closure times will be issued closer to each stage.

Work impacts on commuters

  • Extended periods of temporary traffic lights.
  • Daytime closures with pedestrian access provided. Please follow staff instructions when walking through the site.
  • Two days of hard daytime road closure, between 9am and 3pm, with no vehicle or pedestrian access during the installation of the concrete panels. Tentative dates for closure will be 2 and 3 of June, with contingency to slide through to 10 June subject to weather and unforeseen issues. Updated signage and letter drop notification will be provided one week prior to closure to confirm timing.
  • Increased noise, dust and vibration from excavation, drilling, machinery and increased truck movements.

Access requirements

If you need to travel through the site during a closure period, please speak to our staff on site.

Stay updated

Regular updates will be shared by the contractor via sign board notification, immediately affected letter drop and email, text message if required.

To sign up for these, please contact Downer on 021 379 023.

 

 

 