Whitewash Head Road – retaining walls renewal

What

We will be undertaking construction works to renew two retaining walls located along Whitewash Head Road.

Why

The retaining walls have reached the end of their design life and need to be replaced for safety issues and to keep the current level of services.

Where

Whitewash Head Road between number 4 and 6 and by number 16 and 18, Scarborough.

When

6 May 2026 to early October 2026. Monday to Friday, 7am to 6pm (weather/site condition dependent). Please note that some Saturday work may be required as dictated by project requirements.

Contact

The contractor is Hunter Civil. Phone Jess Baker on 021 028 40199, Monday to Friday, 8am to 5pm or email jess@huntercivil.co.nz.

Details

Hunter Civil will perform construction works of two walls along Whitewash Head Road. There will be traffic management in place while they carry out this work.

While this is in place:

  • The road will be closed to all vehicles between 8.30am and 4pm Monday to Friday. Before and after these closure times, the work areas will be fenced off and access for vehicles will be restored.
  • We will reduce the traffic management impact when it is safe to do so and communicate this with residents via a group correspondence system.
  • Pedestrian access will be maintained during the road closure, either by a delineated path or escort past the work site (depending on space), please follow the signage.
  • Rubbish/recycling bin collection will be completed on your collection day outside of closure times.
  • Please advise if you have any specific property access requirements e.g. medical visits, home help, large vehicle access, deliveries, planned work etc.
  • The work may result in increased dust, noise and vibrations. We will try to keep any disruptions to a minimum and apologise in advance for any inconvenience. 

 

 

 