Main North Road - road resurfacing (NIGHT WORKS)

What

We will be resurfacing the road to ensure a resilient, smooth and strong surface.

Why

Resurfacing adds grip, strength and resilience to our roads.

Where

Main North Road between Dickeys Road and QE11 Drive.

When

28 April 2026 to late May 2026. Monday to Friday, 7pm to 5am (weather/site condition dependent). No work will take place on Saturday nights.

Contact

The contractor is HEB Construction Ltd. General Enquiries: Phone 0800 432 226, Project Manager - Harshil Patel: Phone 027 325 3559, Monday to Friday, 8am to 5pm.

Details

We will be resurfacing sections of the road with a new asphalt surface. This work will take place in three stages over a period of about four weeks.

  •  Stage 1: Johns Road to Dickeys Road 
  • Stage 2: Styx Mill Road to south of the Johns Road intersection
  • Stage 3: QEII Drive to just north of the Lowry Avenue intersection 

 Access to property during the work: 

  •  Access to residents’ driveways will be maintained but may be impacted at times. Footpath access will remain open.
  • There will be traffic management spotters in place during our work hours to assist you move safely through the site when required.
  • Please advise HEB Construction staff in advance if you need access to and from your property during the closure period, and they will do their best to make access available for you.
  • When needing to enter or exit your property during work hours, please signal to staff for their assistance – you can do this even if you have not advised HEB in advance.

 