Hamilton Avenue - Waimairi Stream bank renewal

What

We will be installing streamside rock retaining with naturalised native planting to retain the stream bank. Selected trees and vegetation are needed to be removed so this can be completed.

Why

The existing timber drain is past the end of its usable life. The rock edging will retain bank soil, supporting long term dependable land drainage through this area. Native planting between the rocks will hold soil in place and improve the streamside setting.

Where

49 and 47a Hamilton Avenue, Ilam

When

19 March 2026 to 1 May 2026, Monday to Friday 8 am to 6 pm (weather/site condition dependent).

Contact

The contractor is City Care Limited. Phone Mikaela Abraas on 022 017 3972, Monday to Friday 8am to 6pm.

Details

  • All the works are to be undertaken off street but will include entry to 49 Hamilton Avenue.
  • Traffic and pedestrian management will be in place to ensure safe vehicle and plant entry and exit at the property.
  • The footpath may be closed for short intervals when trafficking is to occur. Our contractor will provide guidance to any affected pedestrians.
  • Localised noise will increase at time but will be minimised where possible and undertaken at considerate times of the day.

 