13 Hackthorne Road – retaining wall renewal

What

Construction of a new retaining wall at 13 Hackthorne Road.

Why

The retaining wall was damaged during the earthquakes and has now reached the end of its design life. It must be replaced to address safety concerns.

Where

13 Hackthorne Road, Cashmere.

When

2 March 2026 to late April 2026. Monday to Friday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is Isaac Construction. Phone 027 553 0112, Monday to Friday, 8am to 5pm or email communications@isaac.co.nz.

Details

We will be constructing a new retaining wall at 13 Hackthorne Road from 2 March 2026 until the end of April 2026. Traffic management will be in place for the duration of the works.

While traffic management is in place, please note the following:

  • Two-way traffic will be maintained at all times.
  • There will be closures of the footpath and road shoulder in the work area. As a result, on-street parking will not be available in this section, and pedestrian detours will be provided.
  • We will maintain property access for residents, where possible, during the day. Our on-site team will communicate directly with affected residents regarding any temporary access restrictions.
  • At night, the site will be secured with fencing, and full property access for residents will be restored.
  • A 30km/h speed limit will be in place to ensure the safety of both our team and road users.
  • Please follow all signage and detours in place.
  • We will reduce the extent of traffic management as soon as it is safe to do so.
  • Please advise if you have any specific property access requirements e.g. medical visits, home help, large vehicle access, deliveries or planned works etc.