Hawthorne Street, Walnut Avenue and Lansbury Avenue - wastewater main renewals

What

We’re replacing the wastewater network under the roads and footpaths.

Why

The local wastewater network has reached the end of its serviceable design life and therefore is due for replacement.

Where

Hawthorne Street, Lansbury Avenue and Walnut Avenue, Fendalton.

When

10 November 2025 to late June 2026. Monday to Friday, 7am to 6pm (weather/site condition dependent).
(Note: some Saturdays may also be worked pending works progression over the scope)

Contact

The contractor is LB Civil. Phone Kieran Davis on 027 245 5752 or email kieran@lb-civil.com, Monday to Friday, 8am to 5pm.

Details

Traffic impacts / property access

First stage: Walnut Avenue and Hawthorne Street

To enable works to occur through this area we will require a temporary road closure from 7am to 5:30pm, Monday to Friday, starting Monday 10 November and continuing for approximately one month. We ask that during the working hours listed that cars are parked outside of this area on Hawthorne Street. Pedestrian access to properties will be maintained at all times during working hours. Outside of working hours, access will be restored.

Next stages: Walnut Avenue and Hawthorne Street

  • As the works progress further within Walnut Avenue, Hawthorne Street will reopen, and we will work to open sections of Walnut Avenue to residents access where able to do so. Vehicle access will still be limited to none through these stages, but we will do our best to accommodate residents as much as possible as the project progresses.
  • Please let us know if you have any specific property requirements e.g. medical visits, home help, large vehicle deliveries, planned works etc. and we’ll do our best to make sure you are accommodated.
  • In case of an emergency, access will be provided to emergency vehicles, please notify one of our crew on site and we’ll do our best to give you access. If driving through, please ensure you’re being directed by an appointed person on site at all times.

Further notifications

  • As the project progresses, we’ll do some additional letter drops to keep you informed of upcoming stages and any property access impacts along Hawthorne Street and Lansbury Avenue.

Other details

The scope of works involves trenching 800 metres of a new wastewater main, and the laterals that will connect them to your properties. We’ll also be digging small potholes along the road, footpaths and berms to find the location of existing services. This potholing work involves a specialised equipment called a hydro-truck, which can be noisy. We apologise in advance for any inconvenience this may cause.

All this will involve pumping underground water, trenching and excavation works. At the end of this project, we’ll reinstate the section of road we’ve worked on with new asphalt. 

Our schedule will depend on the weather and the condition of the roads. We’ll provide updates if there are changes to the planned works.

We know this work is disruptive, and we appreciate your co-operation and understanding over this period.