What |
As part of our project to install larger wastewater pipes through Ilam, the next phase of work will involve traffic management at the intersection of Maidstone Road and Waimairi Road. |
---|---|
Why |
We’re installing new, larger wastewater pipes through Ilam to help meet the increasing demands of our growing city. These essential upgrades will improve the capacity and resilience of the wastewater network. |
Where |
Intersection of Maidstone Road and Waimairi Road, Ilam. |
When |
20 October 2025 to 19 December 2025. Monday to Saturday, 7am to 6pm and some night works Monday to Thursday, 9pm to 6am (weather/site condition dependent). |
Contact |
The contractor is Dormer Construction. Phone Emma Dormer, 0508 DORMER or email emma@dormer.co.nz, Monday to Friday, 8am to 5pm. |
This significant wastewater pipe upgrade started in September 2025 and will be finished by early 2026. Parts of this upgrade are now completed (Clyde and Creyke Roads), and work is ongoing on Maidstone Road.
From 20 October 2025, the contractor will start with trenching and excavation works at the intersection of Maidstone and Waimairi Roads. This phase of work will take approximately 9 weeks to complete. The final phase of the project will then follow in early 2026, with the main focus being minor tidy up works. The Maidstone Road westbound one-way system may be required for a short time if work on Maidstone Road isn't complete, but we will be trying to finish up there before Christmas also. The previous works notice stated that this impact could be in place until approximately mid-2026, but with the project progressing well, we know that it would be early 2026 at the latest.
Works include:
Key works on existing watermains will be completed at night between 9pm and 6am (Monday to Thursday) to reduce disruption to the service when demand is low. Where a water shut-off is required, notice will be given to affected properties 48 hours prior.
Traffic impacts
The main traffic impacts during this next phase are:
Signposted detours will be in place around the intersection and Maidstone Road for affected traffic.
A 30km/h speed limit will be in place so we can keep our workers and everyone safe.
Please follow the signage and keep an eye out for changes in traffic management.
Additional information
Stay updated on the project at Ilam wastewater upgrade(external link).