What |
We are renewing and upgrading the existing stormwater drain, which is an open, timber-lined drain. |
---|---|
Why |
This renewal is required to replace deteriorated infrastructure. Some of the old timbers are slumping, and the surrounding banks also need extra supports to keep them stable. |
Where |
Johns Drain, Christchurch (as depicted below). |
When |
Construction is scheduled to start early October 2025 with an expected duration of approximately 15 weeks. |
Contact |
The contractor is City Care Ltd Mikaela Abraas. Phone 022 0173972, Monday to Friday, 7am to 6pm, Saturday 8am to 12pm, or email mikaela.abraas@citycareproperty.co.nz. |
We will be renewing the timber lining along sections of John’s Drain to stabilise the existing banks and address areas that are failing and slumping.
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Book an indoor or outdoor space.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Book an indoor or outdoor space.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch