What |
We’ll be working to replace broken pavers between and around the tram tracks. A road closure will be in place at all times during the works. |
---|---|
Why |
Due to water getting underneath the pavers, the pavers are damaged and need replacing. |
Where |
Corner of High Street and Poplar Street, Central City. |
When |
6 October 2025 to 19 October 2025. Monday to Friday, 7am to 6pm (weather/site condition dependent). |
Contact |
The contractor is Fulton Hogan. Phone 0800 7623 34 (0800 ROAD FH), Monday to Friday, 8am to 5pm, or email cant.info@fultonhogan.com. |
Christchurch City Council is planning to carry out paving repairs near the corner of High Street and Poplar Street, in the area between and surrounding the tram tracks.
Recent inspections have identified that water has seeped beneath the pavers, causing the surface to deteriorate. A temporary asphalt repair was completed by the Council Maintenance team to ensure safety and accessibility in the short term.
We will now be returning to remove the temporary asphalt and relay the pavers in this section. Works will include breaking out the asphalt and some of the concrete below and laying the new pavers. The new pavers feature an updated herringbone design that will help reduce the risk of future failures.
*The work is expected to take approximately two weeks to complete, from Monday 6 October to Sunday 19 October 2025. Most work will be carried out from Monday to Friday, but there may be some works at weekends if required.
Traffic Impacts
Road Closure Map
Other details
Please advise us via the contact information above if you have any specific property requirements e.g. medical visits, home help, large vehicle deliveries, planned works.