What |
We are progressing work on all fronts, with just minor works to go on Aorangi Road (north of Wairakei Road) and Wairakei Road, allowing more access to be reinstated during September. Major works and traffic impacts continue on Aorangi Road (south) until December, when Stage 1 (of 3) of this project will be complete. |
---|---|
Why |
We are doing this work to upgrade old wastewater and water supply infrastructure; to make the roads safer and more accessible for cyclists and pedestrians; and to reconstruct the road and footpaths, which are in need of renewal. |
Where |
Aorangi Road, Condell Avenue to Bateman Avenue, Bryndwr. |
When |
Mid-September 2025 to December 2025. Monday to Saturday, 7am to 6pm (weather/site condition dependent). |
Contact |
The contractor is Isaac Construction. Phone 027 323 0056 or email MCRnorwestarc@isaac.co.nz, Monday to Friday, 8am to 5pm. |
Over the past eight months, our crews have completed all major work along Wairakei Road, including the commissioning of the new traffic lights and upgrades to the watermain, wastewater, and streetscape. By late September, work on Aorangi Road (north) will also be at the same stage, with the new cycleway ready for use.
For the remainder of 2025, minor works will continue along Wairakei Road and Aorangi Road (north). These works are expected to have minimal impact on vehicle, pedestrian, and cyclist movements in the area.
Upgrades along Aorangi Road (south) are ongoing, as is the temporary southwest-bound one-way system. The worksite will be reduced where possible as crews progress through the main stage of construction.
Aorangi Road (north), between Condell Avenue and Wairakei Road
Mid-September onwards:
Late September onwards:
Aorangi Road (south), between Wairakei Road and Bateman Avenue
Work on the stormwater, wastewater, cycleway, and street upgrades will continue through till December 2025.
Mid-September onwards:
Information for residents and businesses within work areas: