What |
We are undertaking a street renewal for Brockworth Place including wider footpaths, upgraded stormwater drainage, new landscaping and street trees and road re-sealing. |
---|---|
Why |
Brockworth Place is in poor condition and needs renewing. This project has been funded through CRAF (Christchurch Regeneration Acceleration Facility) which is a funding package from Central Government for transport projects. |
Where |
Brockworth Place, between the cul-de-sac and Deans Avenue, Riccarton. |
When |
7 July 2025 to the end of September 2025. Monday to Friday, 7am to 5pm (weather/site condition dependent). |
Contact |
The contractor is Fulton Hogan. Phone 0800 762 334, Monday to Friday, 8am to 5pm or email cant.info@fultonhogan.com. Please call us out of hours if the matter is urgent. |
What are we doing?
We are reconstructing the road surface on Brockworth Place, including the installation of new stormwater pipes, new kerb and channel, new landscaping and street trees, footpath upgrades and a new road surface. We will also be installing new line marking and tactile pavers once the road reconstruction is complete.
Traffic impacts
Resident parking
Due to the daily closure of Brockworth Place - between cul-de-sac and Deans Avenue, we have had on-street parking on Brockworth Place (north of our work site) and on Deans Avenue, between Mayfair Street and Brockworth Place approved for residents.
Please display the permit provided on your dash, which will provide an exemption from compliance. If you require more than two permits, please contact us on the email address provided. The parking permits will be delivered to your letterboxes prior to the work starting.
Please send your number plate to cant.info@fultonhogan.com e.g. ABC123.
Work site
We are aware of the cabling project elsewhere in Brockworth Place. These street improvements are a separate project.