What |
We’re making a number of safety upgrades in the Bromley area. |
---|---|
Why |
These upgrades will improve the safety and accessibility of these streets in the Bromley area. |
Where |
Six areas in Bromley, including the intersections of Keighleys Road and Bromley Road, Keighleys Road and Korora Street, Keighleys Road and Bromley Road. Please see the map below for each work area. |
When |
Monday 23 June 2025 to Friday 18 July 2025. Working from Monday to Saturday, 7am to 7pm (weather dependent). |
Contact |
The contractor is Isaac Construction. Enquiries to Hayley Ching on 027 323 0056 or via email at communications@isaac.co.nz, Monday to Friday, 7am to 6pm. |
From Monday 23 June, we'll begin making road safety upgrades across six work areas in Bromley (please find a map of these locations below).
We're making these upgrades in response to road safety concerns shared by the local community and considered in the Bromley Transport Action Plan. The first phase of work from the Action Plan is funded in the Christchurch City Council's Long Term Plan 2024 to 2034.
Improvements across six work areas include:
Work areas are:
We’ll begin in 'Work area 1' and continue southeast, towards 'Work area 6'. We anticipate the work in each area will take approximately two to three days, depending on the weather. For a full list of traffic impacts, please see below.
Stay up to date on this work by visiting: ccc.govt.nz/bromley-transport-action-plan(external link)
Traffic impacts:
Our Work areas:
We know roadworks can be disruptive and we appreciate your cooperation and understanding.
Ngā mihi nui, thanks for your patience while we make these road safety upgrades for Bromley.