Glenroy Street - texturising of asphalt

What

Road closure for half a day to install the texturising on top of the asphalt in the Glenroy Street Road corridor.

Why

To match the existing road material.

Where

56 Glenroy Street to the intersection of Glenroy Street and St Johns Street.

When

29 April 2025 to 2 May 2025, 11am to 4pm (one day only, weather/site condition dependent).

Contact

The contractor is Seipp Construction. Phone 03 660 0315, Monday to Friday, 8am to 5pm.

Details

  • Christchurch City Council has contracted Seipp Construction to undertake the construction of an underground scour pipeline along the road corridor from 56 Glenroy Street through to the intersection of St Johns Street.
  • There will be a road closure required to undertake the texturizing of the existing asphalt trench.
  • This will be in place between 56 Glenroy Street and the Glenroy Street/St Johns Street intersection.
  • This will result in no-parking within the traffic management area.
  • The total duration of the road closure will be 5 hours, between 11am and 4pm. 
  • It is currently planned for Tuesday 29 April, but this is weather dependant, so could be delayed to one of the days following.
  • Thank you for your patience as we upgrade the roading network in your area.

 