What |
We’ll be installing a safe speed platform on Cranford Street. |
---|---|
Why |
We’ve identified a safety issue at the pedestrian crossing on Cranford Street. Installing this safety feature will help to protect everyone travelling through the area, including people walking, biking and scooting to school, preschool or local shops. |
Where |
The intersection of McFaddens Road / Cranford Street (northbound lane), St Albans. |
When |
Sunday 16 February 2025 *NIGHT WORKS* 6pm to 6am, and Monday 17 February 2025, 6am to 6pm (weather/site condition dependent). Find more timing information below. |
Contact |
The contractor is Fulton Hogan. Phone 0800 7623 34 (0800 ROAD FH), Monday to Friday, 8am to 5pm, or email cant.info@fultonhogan.com. After business hours, please feel free to call us if the matter is urgent. |
Project background: A safety issue has been identified at the intersection of McFaddens Road and Cranford Street. Currently, drivers exiting McFaddens Road are looking to the right along Cranford Street to choose a gap to join the traffic. When pulling out in a hurry, drivers sometimes miss the traffic signals at the pedestrian crossing, and drive through the crossing when the signals are on red.
In response, we’re installing a safe speed platform before the pedestrian crossing on Cranford Street. This will encourage drivers to travel at a safer speed, providing people more reaction time and reducing the risk of a crash with a person crossing at the lights.
Why we’re back: We recently completed the speed hump at the entrance to McFaddens Road to slow turning traffic and the related kerb and channel works. Due to wet weather, we were unable to complete the safe speed platform at the same time and need to return to finish these works. We’ll also be completing the remaining line marking at the same time.
Due to the busy traffic on Cranford Street, we’ll be undertaking the first half of these works (road resurfacing) overnight. This will help us to carry out the work safely and efficiently to limit disruption.
This work is highly weather dependent, if the weather is poor the work will be rescheduled to the following night.
Timing: This work involves night works and day works as follows:
Find more information about the traffic impacts, and a map of the work area, over the page.
Contingency dates: This work is highly weather dependent. If the weather is poor, work will be rescheduled to:
Future work: We will need to return for one night in mid-May to complete the coloured surfacing. Another notice will be distributed for that work closer to the time.
Traffic impacts
The following will be in place for the duration of these works:
The traffic impacts on Cranford Street apply as follows:
Other details