Te Kaha Surrounding Streets – transport and water upgrade

Update

What

We are upgrading the water network and transport infrastructure around One New Zealand Stadium at Te Kaha.

Why

To support the growing south-east central neighbourhood and to get ready for One New Zealand Stadium to open in 2026, we are upgrading the water infrastructure and transport network in the area.

Where

Lichfield Street (Manchester to Madras), Madras Street (St Asaph to Hereford, including intersections), Barbadoes Street (Gloucester to Ferry, including intersections), Tuam Street (Madras to Barbadoes), Cashel Street (Manchester to Madras) and Ash Street (off Madras).

When

29 July 2024 to late November 2025. Monday to Saturday, 7am to 7pm (weather/site condition dependent).

Contact

The contractor is Isaac Construction. Phone 0800 ISAACC (472 222), Monday to Friday, 7am to 7pm or tekaha.streets@isaac.co.nz. Please advise the contractor if you have any specific property access requirements.

Details

Work is underway at several locations around the stadium and includes upgrading the water infrastructure, widening footpaths, landscaping, improving pedestrian crossings, and changing the travel direction of some streets.

Works will take place on:

  • Barbadoes Street (between Gloucester Street and Ferry Road).
  • Madras Street (near the St Asaph Street intersection, continuing north).
  • Lichfield Street (working from Madras Street towards Manchester Street).
  • Tuam Street (near the Madras Street intersection, continuing east to the Barbadoes Street intersection).
  • Ash Street (off Madras).
  • Cashel Street (between Manchester Street and Madras Street).

Traffic Impacts:

  • Most of our work will take place between 7am - 7pm, Monday to Friday, with some work taking place on weekends as required.
  • At times, night work may be required. You will receive further notification from the contractor prior to this happening.
  • Temporary traffic management (road cones, signs) will be installed as part of the works. There may be some traffic delays. Please follow all signage and instructions from our team onsite.
  • There will be no on-street parking while we are working in the area.
  • At times, there will be a reduction in lanes, shoulder closures and closures of turning lanes.
  • At times, we will use manual traffic controls to support the flow of traffic while we work in the road.
  • At times, the east to west running streets (e.g. Gloucester Street and Worcester Street) will be reduced to one-way or closed through the intersections with Barbadoes Street and Madras Street. Detours will be in place where appropriate.
  • Those who commute across the city are encouraged to use alternative routes e.g. Fitzgerald Avenue or Montreal Street during the construction works.

Information for residents and businesses:

  • The nature of the work that we are doing will generate noise, dust and vibrations.
  • At times, several footpaths and pedestrian crossings will be closed while our crew is working. When this happens there will be traffic controllers on hand to escort pedestrians across the road.
  • Access to residences and businesses may be temporarily impacted at times, but our crew will make access available as soon as possible.
  • Please advise if you have any specific property access requirements e.g. medical visits, large deliveries, home help and any planned works.
  • This work will require several planned water shut-offs. You will receive further notification from the contractor prior to this happening, if you are affected.
  • Please put your bins out as usual by 6am on your collection day. Our team will move them and return them, if needed.


Learn more at ccc.govt.nz/tekahastreets