What |
We are upgrading the water network and transport infrastructure around One New Zealand Stadium at Te Kaha. |
---|---|
Why |
To support the growing south-east central neighbourhood and to get ready for One New Zealand Stadium to open in 2026, we are upgrading the water infrastructure and transport network in the area. |
Where |
Lichfield Street (Manchester to Madras), Madras Street (St Asaph to Hereford, including intersections), Barbadoes Street (Gloucester to Ferry, including intersections), Tuam Street (Madras to Barbadoes), Cashel Street (Manchester to Madras) and Ash Street (off Madras). |
When |
29 July 2024 to late November 2025. Monday to Saturday, 7am to 7pm (weather/site condition dependent). |
Contact |
The contractor is Isaac Construction. Phone 0800 ISAACC (472 222), Monday to Friday, 7am to 7pm or tekaha.streets@isaac.co.nz. Please advise the contractor if you have any specific property access requirements. |
Work has been underway at several locations around the stadium since August 2024.
Works include upgrading the watermains and wastewater network, widening footpaths, landscaping, improving pedestrian crossings, and changing the travel direction of Lichfield Street and Tuam Street, east of the stadium.
Works are happening on:
Traffic Impacts:
Information for residents and businesses:
Learn more at ccc.govt.nz/tekahastreets