Sumner Seawall Repairs - update

Update

What

Pavement upgrade and resurfacing works of the Sumner Promenade.

Why

To provide a smooth asphalt finish.

Where

Between Cave Rock and the Scarborough Clock Tower, Sumner.

When

16 September 2024 to mid October 2024. Monday to Friday, 7am to 7pm (weather/site condition dependent).

Contact

The contractor is Fulton Hogan. Phone 0800 762 334 (0800 ROAD FH), Monday to Friday, 8am to 5pm or email cant.info@fultonhogan.com. After business hours, please feel free to call us if the matter is urgent.

Details

  • As we approach the completion of the rock revetment works, we will start to re-build isolated sections of the Promenade, before applying an asphalt surface. The exposed soil in the landscape shoulder will be grassed to help stabilize the soil over summer.
  • The Promenade will need to be closed from Monday to Friday as we undertake this works, however, will be opened back up over the weekend where it is safe to do so.
  • Pedestrian access to the beach will be maintained where possible; please use the designated access points where existing steps/ramps are located.
  • Possible delays to pedestrians when trucks are crossing access points.  Please follow the directions provided by the onsite traffic management team at all times.
  • Construction noise and disturbance may be encountered but the contractor will endeavour to keep this to a minimum.
  • Trucks will access site from Heberden Avenue and exit on to the Esplanade Road by Scarborough, so there may be minor traffic delays in this area.