Halswell Junction Road Extension - road closure

What

Road closure.

Why

KiwiRail works on the railway require the level crossing to be closed for safety.

Where

Intersection of Halswell Junction Road and Waterloo Road at the railway crossing.

When

Works start here Saturday 27 July 2024 to Monday, 29 July 2024, 7am to 7am (weather/site condition dependent).

Contact

The contractor is Fulton Hogan. Phone 0800 7623 34 (0800 ROAD FH) 24 hours or email cant.info@fultonhogan.com.

Details

As part of the Halswell Junction Road Extension project, KiwiRail are working on the railway on Saturday 27 to Monday 29 July 2024. These works require a level crossing and road closure on Halswell Junction Road at its intersection with Waterloo Road at the railway crossing to keep everyone safe, see map below:

 

Traffic Impacts

The road closure will be in place on Saturday 27 July to Monday 29 July. There will be no access across the railway at this time so please follow the detour signs on site.

The road closure will be removed as soon as our work site permits it. Please look out for our staff and follow their instructions. A 30kph speed limit will be in place to keep everyone safe. We know this work is disruptive, so we appreciate your patience and understanding. Thanks for your cooperation whilst this work is undertaken.

Driveway access

Access to properties will be maintained. However, we may need to work in front of driveways from time to time. We will try to give you plenty notice of this. However, if you need to get into or out of your property and we are in the way, please just talk to one of our friendly staff and we will make sure you can use your driveway.

Next stage- Information from CCC

KiwiRail is currently completing works on the railway with line closures booked for July (this notice) and August 2024. KiwiRail is progressing works between line closures as part of delivering the project, and a further line closure will be required for the new level crossing to open and the existing level crossing to be closed to all traffic.

 KiwiRail is planning these works currently and the aim is to complete them by the end of 2024. Traffic will then be able to use the new link road to travel north on Halswell Junction Road.

 Once the new level crossing is open, Fulton Hogan will return to construct the cul-de-sac section of Halswell Junction Road, which will have a new road name and numbering.

 The new road name for the cul-de-sac is Panther Place, as decided by the Waipuna Halswell-Hornby-Riccarton Community Board in December 2023

 