Okains Bay Landfill - sea wall repairs

What

We are remediating the damaged sea wall alongside the edge of the Okains Bay Landfill.

Why

The existing sea wall is damaged, and the landfill is starting to erode. This section of sea wall is no longer deemed fit for purpose.

Where

Okains Bay Landfill is located on Okains River Road, Okains Bay, Banks Peninsula.

When

4 June 2024 to 5 July 2024. Monday to Friday, 7am to 6pm, (weather/site condition dependent).
Some out-of-hours work may be required to work around weather and tidal constraints.

Contact

The contractor is Fulton Hogan Ltd. Phone 03 336 5268, Monday to Friday, 7am to 7pm.

Details

Work details

The rock revetment works will involve supply and placement of large rock along the foreshore along the existing sea wall. 

The rock will be sourced locally within Banks Peninsula.

Upon completion, the work area will be top-soiled and grassed where required.

Impact of work:

The work will be noisy while we complete the rock placement works.

Some on-street parking and berm area will be restricted on Okains River Road for safety reasons.

There will be an increased number of trucks moving through Okains Bay and Summit Road.

Public access to this area will be temporarily restricted while the work is being undertaken.

 