Ferry Road - stormwater renewal works

What

Brick barrel stormwater drain renewal works and traffic management system.

Why

The brick barrel stormwater drain running beneath Ferry Road has been identified as having damage, threatening the structural integrity and water tightness of the drain.

Where

304A Ferry Road extending to 322 Ferry Rd with a road closure in place for Osborne Street, Waltham.

When

Monday 4th December to Friday 22nd December 2023. Monday to Saturday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is Seipp Construction. Phone 03 660 0315, Monday to Friday, 8am to 5pm.

Details

  • Our contractor, Seipp Construction, will be installing a new manhole to accommodate future lining works to renew sections of the brick barrel drain running beneath Ferry Road.  
  • The manhole works are necessary to provide access to install the new lining.  Lining works are due to take place in March 2024.
  • While manhole works are underway, traffic management will be in place. This will include vehicle restrictions in and out of Osborne St. Two lanes of traffic will be maintained on Ferry Road with speed restrictions and cyclists merging. Property access will be maintained for most properties. However directly outside the works will be affected with restricted vehicle access.
  • Safety is our number one priority – and it’s your responsibility, too. Stay clear and stay alert. Please keep children and pets at a safe distance from the worksite. 
  • We apologise for any inconvenience this may cause.