What |
Repair of cracks, potholes, kerb and channel and other road damage. With final surfacing to be applied at a later date once repairs have settled. |
---|---|
Why |
Maintenance reduces the likelihood of potholes, makes the road safer and improves the overall road condition. |
Where |
Olivine Street |
When |
25 September 2023 to 7 October 2023. Monday to Friday, 7am to 7pm (weather/site condition dependent). Some works may be required outside these hours. |
Contact |
The contractor is HEB Construction. Phone 027 260-3619, Monday to Friday, 7am to 7pm. |
Work on Olivine Street will be carried out in two stages.
Stage one. Contractor will repair kerb and channel, cracks, potholes, kerb and channel damage and any additional road damage.
Once repairs have had time to settle, the final surfacing layer over the whole area will be applied. This could mean up to six months before the final resurfacing is applied. We’ll be in touch again before stage two.
This work may cause noise and vibration at times, but we will make every effort to keep disruption to a minimum. We apologise for any inconvenience and appreciate your patience while we do this work.