Cashmere/Hoon Hay/Worsleys Roads - intersection upgrade

What

We’re upgrading the intersection at Cashmere, Hoon Hay and Worsleys Roads and installing traffic lights.

Why

To make it safer and easier for pedestrians, cyclists and motorists to cross the road at the intersection.

Where

Cashmere/Hoon Hay/Worsleys Roads intersection. There will also be traffic calming works on Blakiston Street, Mavin Road, Kaiwara Street and Hurunui Street.

When

Work will start in April 2021 and is expected to be completed by late August 2021 (weather dependent). Work will be undertaken between Monday to Saturday, 7am to 6pm.

Contact

The contractor is HEB Construction. Phone Gearoid Coholan on 027 703 4871 between Monday to Saturday, 7am to 6pm. After hours phone 03 313 7601.

Details

  • This upgrade work will involve a full reconstruction of the intersection including new kerbs, drainage pipes, footpaths and landscaping.
  • Parts of this work will be noisy with some noise coming from trucks, heavy machinery and workers along the road as we locate existing services and upgrade the road and surrounding area. We will provide plenty of notice around this at the time.
  • There will be some disruption to traffic using the intersection during construction and, if we do need to close the roads, there will be clear traffic management and detours in place so you'll know where to go.
  • For more information on the project visit: 
    ccc.govt.nz/cashmere-worsley-and-hoon-hay-intersection-upgrade(external link)
  • Thank you for your patience while we upgrade the intersection.