Aldwins Well Head Upgrade - Aldwins Road

Update

What

Our Contractor will be upgrading the well heads at Aldwins Pump Station site so that the local Aldwins Pump Station can supply unchlorinated drinking water.

Why

The water from the pump station is currently being treated with chlorine. Once this work is completed, the water will no longer need chlorine treatment.

Where

Aldwins Pump Station, Corner of Aldwins Road and Bass Street.

When

Work will start 4 July 2019 through to mid-September 2019.

Contact

The contractor is Seipp Construction Limited. Phone Greg Valentine (03 423 1718) between 8.00am and 5.00pm Monday to Friday.

  • Work will be undertaken at the Aldwins Pump Station over the next two months, upgrading two below-ground well heads.
  • The work will allow the pump station to supply residents and businesses in the area with safe, unchlorinated drinking water.
  • No traffic impacts are expected as all works will be contained inside the pump station area, located at the corner of Aldwins Road and Bass Street. (please refer to Map).