Stormwater work
A brick barrel stormwater drain, constructed pre 1900s, lies beneath Ferry Road. Sections of the brick barrel drain are damaged and need to be repaired. Repairs include installing new manholes, repairing existing manholes and installing pipe lining. Installation of the lining will be done through the newly constructed manholes.
The installation and repair of the manholes will require excavation of the road.
We’ve scheduled the installation of the pipe lining for early March, as the brick barrel needs to be dry and clean before the liner can be applied. The installation work will take between 8 to 25 days per manhole site.
Manhole work
We need to construct five new manholes over the brick barrel stormwater drain to create access for installing the lining. Our contractors are working to minimise the impact on the affected communities in the area as much as possible.
Work on the first manhole (A) began in early December 2023 near Osborne Street. Work will stop before Christmas to avoid disruption to local businesses and recommence on 8 January 2024.
Traffic changes
While the construction works are in progress, all traffic lanes on Ferry Road, Ensors Road, and Aldwins Road will be maintained with speed restrictions. Speed will be lowered to 30km/h near the construction sites.
While work is in progress on manhole B and manhole C, there will be right-turning restrictions at the intersection and side roads.
There will be no right turns from Ferry Road into Aldwins Road (coming from the east) and into Ensors Road (coming from the west). See map below.
Map of manhole works
Manhole | Description |
A | Work began in December 2023 and will take three weeks. |
B | Work began on 8 January 2024 and will take up to 6 weeks. |
C | Work began on 8 January 2024 and will take 14 days. Restricted access to Hart Street, with resident access maintained. |
D | Work begins once manhole C is completed and will take 14 days. |
E | Work begins once manhole D is completed and will take 14 days. |
Download the full works notice [PDF, 54 KB].
Transport work
The traffic signals at the intersection of Ferry/Ensors/Aldwins roads need full replacement including underground cables because they’ve reached the end of their working life.
There are also plans to make safety improvements to the intersection by installing safe speed platforms.
The intersection upgrade was consulted on earlier this year and approved by the Council in September 2023.
At this stage, we’re still working on the timing of these works and can’t yet confirm a start date. The aim is to do some of the transport work in conjunction with the stormwater work to minimise overall construction time and disruption to the area.
However, the majority of the work needs to be done separately due to traffic management needs and limited space.
The transport work will likely take about six to seven weeks to complete. We’ll update you again when we have more certainty on the timing.