88 Hinau Street - retaining wall naturalisation

What

Removal of retaining wall and naturalisation of Ilam stream.

Why

This retaining wall has reached the end of its economic design life and needs to be replaced.

Where

Ilam Stream between 88 and 88C Hinau Street.

When

Work will start in late March 2021 and is expected to be completed by early May 2021 (weather and on-site condition dependent). Work will be undertaken between Monday and Friday, 7am to 6pm.

Contact

The contractor is City Care Ltd. Phone 0508 248 922 between Monday to Friday, 7am to 6pm.

Details

  • Access will be maintained at all times as work is from private property 
  • There may be increased dust and noise during the works which we will try to minimise as much as possible