Canterbury Multi Use Arena - Civil Enabling Works

What

On the streets immediately around the new multi-use arena, we are making changes to existing services.

Why

These changes are required to allow existing water, stormwater and wastewater services to meet the future needs of the new multi use arena.

Where

This will occur from Barbadoes St to Madras St, and Lichfield St to Cashel St (inclusive).

When

Work will start on 2 November 2020 and is expected to be completed by late January 2021.

Contact

The contractor is City Care Ltd. Phone 0508 248 922. Please advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works.

Details:

Generally all works will be limited to the intersections. A section of Madras St (Cashel St to Bedford Row) will also have work undertaken between the intersections. No full closures to traffic are planned, however traffic lanes will be reduced. No night time work is planned however if the need arises for night works, then a separate notification will be made.

As water supply changes are made, a separate notice will be delivered to affected properties, which will detail the day/time of any planned shutdown.