Lincoln Road Bus Lanes Watermain Upgrade Project. |
---|---|
Why |
To connect new water mains while the road is quieter. |
Where |
Lincoln Road from Hazeldean Road to Harman Street, Addington. |
When |
***NIGHT WORKS: Sunday 26 June to Friday 29 July 2022. Work will be between 6pm until 7am (weather/site condition dependent). |
Contact |
The contractor is Isaac Construction. Phone Peter Chum on 0272366279 or 03 359 9145 or email Lincolnroad2022@isaac.co.nz, Monday to Friday, 7am to 7pm. |
For additional information about the Lincoln Road bus lanes project, sign up to receive eNewsletters or find out more at ccc.govt.nz/lincolnroad
You can also visit isaac.co.nz ‘ongoing projects’ for more specific details about day-to-day operations and to contact the contractor or report any issues.
Impacts on traffic
Impacts of work