Colombo Street - cycleway connection project

Update

What

We are installing painted cycle lanes on Colombo Street, and resurfacing Colombo Street between Kilmore Street and Salisbury Street.

Why

Our network of cycleways is making it safer and easier for people to cycle. When more people are cycling it eases pressure on our roads.

Where

Corner of Colombo Street and Peterborough Street Intersections

When

4 April 2022 to 30 June 2022, Monday to Friday (weather/site condition dependent)

Contact

The contractor is Schick Civil Construction. Phone James Flower on 021 371 272, Monday to Friday,

Details 

This week work will continue at the intersection of Peterborough Street and Colombo Street on the south east corner of the intersection.

The road access closure to Peterborough Street east at Colombo Street will remain in place until the end of the week.

Works being undertaken this week will be focussed on the south east corner of Peterborough Street and include:

  • Kerb and channel installation
  • Planter beds
  • Pavement Construction
  • Footpath Construction

 