What |
We’d like to let you know the end date for this project is now mid-September 2021, instead of August as previously planned. |
---|---|
Why |
A combination of wet weather days, issues locating underground services and the need to replace a section of damaged water pipe on the south side of Cashmere Road. |
Where |
The intersection of Cashmere/Hoon Hay/Worsleys Road. |
When |
Work is now expected to be completed in September 2021 (weather/site condition dependent). |
Contact |
The contractor is HEB Construction. Phone 03 313 7601 between Monday to Saturday, 7am to 6pm. |
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Other projects
Learn more about our work.
ccc.govt.nz/works
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch