Stanmore Road - stormwater pipe repair

What

We are repairing the stormwater pipe in your road.

Why

The pipe repairs are required to stop the road slumping.

Where

288 Stanmore Road, Richmond (directly outside New World Supermarket).

When

27 September 2023 to mid November 2023. Monday to Friday 7am to 6pm and Saturday 7am to 12pm (weather/site condition dependent).

Contact

The contractor is March Construction Ltd. Phone Graeme Inglis, 027 455 7299, Monday to Friday, 8am to 5pm. Please advise if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works.

Detail

  • Temporary traffic management (road cones, signs and barriers) will be in place for the duration of the works.
  • Please follow all traffic management signage and contractor's instructions.  Note, traffic delays may occur.
  • Increased construction noise disturbance may be encountered. The contractor will endeavour to keep this to a minimum.
  • Access to properties will be maintained throughout. 
  • Work will have no impact on any services such as electricity, telecommunication and gas.