What |
We are replacing the water sub-main pipes, which are part of the annual renewals project. |
---|---|
Why |
The existing sub-main pipes have reached the end of their service life and require replacing. |
Where |
Kearneys Road, Linwood. |
When |
27 March 2023 to 30 April 2023. Monday to Friday, 7am to 6pm (weather/site condition dependent). |
Contact |
The contractor is Trenching Dynamics. Phone Daniel Young 0273423488, Monday to Friday, 9am to 5pm. Advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works. |
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.