Braco Place - water mains and sub-mains renewal

What

The renewal of Water Supply mains and sub-mains at Braco Place and Kyeburn Place.

Why

To replace and upgrade existing water mains, sub-mains and lateral connections which has reached its end of lifecycle.

Where

Braco Place, Burnside.

When

24 February 2023 to 31 May 2023. Monday to Friday, 7am to 5pm (weather/site condition dependent).

Contact

The contractor is City Care. Phone John Tuimaunei on 027 231 9294, Monday to Friday, 7am to 5pm.

Details

  • Traffic management will be installed to keep both road users and workers safe
  • Residents will be notified about planned night works and water shut down if necessary
  • Access to properties will be maintained using steel plates where required
  • Please advise us if you have specific access requirements: e.g.:-medical visits, home helps, large vehicle deliveries and any planned works
  • On road parking will be limited during the works
  •  During construction works, both the water supply mains and lateral connections to the property

    boundary will be accessed including work across berms and footpaths