Linwood Park - village remediation

What

The remediation of the temporary village site back to a community sports field area.

Why

This project is to remediate the existing site back to the Council standard for community level sports field use, following removal of the temporary housing village that was established to accommodate persons temporarily after the Canterbury earthquakes in 2010 and 2011.

Where

Linwood Park

When

Mid-November 2022 to late May 2023. Monday to Friday, 7am to 6pm. Saturday, 8am to 6pm (weather/site condition dependent).

Contact

The contractor is Taggart Demolition. Phone Bridgitt Barclay on 027 259 5799, Monday to Friday, 7am to 7pm. Saturday, 8am to 6pm.

Details 

Work is beginning on the remediation of the Linwood Park village area into a green recreational area and community sports field.

The work will involve the following stages:

  • Site clearance and disconnection of remaining services
  • Excavation and removal of the existing asphalt roadway
  • Bulk earthworks to create a re-contoured site
  • Importing topsoil to provide a new sports field surface
  • Installation of drainage
  • Installation of a new irrigation mainline
  • Sowing of grass followed by a grass re-establishment

There will be noise as the contractor moves heavy machinery on to the site in preparation for the work to get underway. We anticipate there will also be on-going noise associated with general construction activity as materials are brought into the site and excavated materials removed. We will be making every effort to minimise the impact of this work as much as possible.

A temporary access way will be made for haulage vehicles to enter the site off Aldwins Road. This will cause some temporary disruption to parking and public access around the perimeter of the site.