We’re upgrading the gateway into New Brighton, including the Pages Road Bridge, which is key to improving the emergency evacuation of the area.
Our plans include better road alignments, road safety upgrades and traffic flow improvements, to make it safer to get in and out of New Brighton. And of course, we want it all to look great too, so landscaping is an important part of the project.
Key changes include a replacement bridge across the Ōtākaro-Avon River, a new T-intersection and traffic lights to replace the Pages Road, Hawke Street and Seaview Road roundabout, Pages Road westbound increasing to two lanes, underground utility and three waters upgrades, and other intersection modifications, kerb buildouts, pedestrian crossings and parking changes.
The new bridge and road will be more resilient to future earthquakes and the effects of climate change. It will be designed to improve access for everyone, from truck and car drivers to cyclists and dog walkers, and everyone in between. And importantly, this project will also provide for large volumes of traffic to exit New Brighton and the surrounding suburbs during planned and unplanned events.
The work to upgrade Pages Road and build the new bridge will require changes to eight nearby roads. These are Hawke Street, Owles Terrace, Hardy Street, Seaview Road, New Brighton Road, Rawson Street, Pratt Street and Keyes Road.
The existing Pages Road Bridge, which was built in 1931 and is the main route across the Ōtākaro-Avon River into New Brighton, suffered significant earthquake damage in 2011.
It is currently operating at about 15% of the New Building Standards so is earthquake prone.
During the earthquakes Pages Road also buckled and dropped in places, affecting drainage. Short-term emergency repairs have served their purpose, but it’s now time for a new bridge, and for the road to be upgraded to be even better than it was before the earthquakes.
The replacement bridge and approach roads will be more resilient, have increased capacity in emergency evacuations and will be built at a higher level allowing for sea level rise and incorporating future stop banks along the Ōtākaro Avon River.
Work in the surrounding area will also provide more walking and cycling connectivity to New Brighton. The current roundabout area will also become a small park featuring the existing palm tree, providing a community facility.
The new bridge and traffic lights will be slightly north of the current position. A benefit of this is to allow the existing bridge to be used while construction is underway.
The entire project is estimated to cost about $80 million (excluding contingencies), and we are working closely with our project partners New Zealand Transport Agency-Waka Kotahi (NZTA), to secure some government funding. Costs will be refined, and more certainty around risks will be defined during the detailed design phase.
The first phase of the funding process was to reach an agreement with NZTA on whether the project aligns with government priorities. This was agreed via a Point of Entry application, which was accepted in October 2024.
In November 2024, the process to compile an NZTA funding subsidy application via a business case commenced. In May 2025, the business case was submitted to NZTA. More information on this process(external link).
NZTA funding subsidy may not be available for all elements of the project, such as the full renewal of the nearby roads, which will be built at a later date when additional funding is available.
The Council has allocated funding through our 2024-2034 Long Term Plan for the project.
Procurement for Detailed design and Construction will commence once New Zealand Transport Agency-Waka Kotahi (NZTA) makes a decision on the funding subsidy application. This is estimated to be around September 2025.
Due to the sensitive nature of the surrounding area, it is likely that gaining consents will take time. Council have already started working with our partners at Environment Canterbury to understand their requirements.
Subject to NZTA funding subsidy business case approval, the elements of the project likely to be designed and built in the first phase of the project will be Pages Road, The New Bridge, The Seaview Rd and Hawke Street T-Intersection, The New Pocket Park and modifications to the nearby road’s intersections in conjunction with the council approved scheme design. The full renewal of the nearby roads will be built at a later date when additional funding is available.
We are currently expecting the design to be complete and consents granted, ready for us to start construction, in the first half of 2028. The project scope mentioned in the first phase above is likely to take between 18 and 24 months to construct.