Water and roading infrastructure in the city’s northwest is being upgraded to make sure these essential services continue to meet the needs of our growing communities.
Starting January 2026, pipe replacement and transport projects in the area will get underway as part of a coordinated work programme spanning two years.
The first project will start in January 2025, and the last project is expected to be completed in March 2028 and include:
We know road works can be frustrating. Combining three waters and transport projects means we can plan the programme to reduce disruption, keep traffic flowing, and get out of the way as quickly as possible.
The first two projects in the Northwest water and roading upgrades programme got underway in January 2026.
Work starts on Memorial Avenue before moving onto Greers Road and heading north to finish just short of the intersection with Wairakei Road.
The work on Memorial Avenue, between 216 and the Greers Road intersection, is expected to be finished by early February 2026. The whole project is due to be completed in July 2026.
Detours and other traffic management will be in place.
The start works notice(external link) has more details.
Work starts on Langdons Road between Oakland Street and the western entrance to Northlink. Traffic on this section of Langdons Road will follow a one-way system westbound.
After the work on Langdons Road has finished, our contractor will move onto Morrison Avenue and progress northwards to the Sawyers Arms Road intersection.
The Langdons Road component will be finished by mid-February, with the whole project due to be completed in mid-April 2026.
The start works notice(external link) has more details.
| Location | Type of work | Start date | Expected end date |
|---|---|---|---|
| Morrison Avenue/Langdons Road | Water supply main, pipe replacement | January 2026 | April 2026 |
| Greers Road/Memorial Avenue | Water supply main, pipe replacement | January 2026 | July 2026 |
| Harewood Road, from Harris Crescent to Greers Road, and Sawyers Arms Road, including Wilmot Street and Chapel Street | Water supply main, pipe replacement | March/April 2026 (estimated) | October 2026 (estimated) |
| Nor’West Arc Major Cycle Route, Matsons Avenue | Cycle lane installation | March/April 2026 (estimated) | November 2026 (estimated) |
| Matsons Avenue, Harewood Road, Chapel Street | Wastewater main, pipe replacement | March/April 2026 (estimated) | February 2027 (estimated) |
| Wairakei Road, between Ilam Road and Greers Road | Water supply main and wastewater main pipe replacement | June 2026 | September 2027 |
| Langdons Road, between Sails Street and Main North Road | Wastewater main, pipe replacement | February/March 2027 (estimated) | November 2027 (estimated) |
| Main North Road, between Mary Street and Proctor Street | Water supply sub-main, pipe replacement | March 2027 (estimated) | June 2027 (estimated) |
| Nor’West Arc, Aorangi Road (between Ilam Road and Brookside Terrace) |
Cycleway installation Wastewater main, pip replacement |
Early 2027 (estimated) | Late 2027 (estimated) |
| Condell Avenue | Road renewal | To be scheduled | To be scheduled |
| Greers Road | Wastewater main, pipe replacement | To be scheduled | To be scheduled |
| Harewood Road | Waster main, pipe replacement | To be scheduled | To be scheduled |
There are a number of other planned projects for the Council that are being coordinated with the Northwest programme in the first few months of 2026:
The map below shows the other projects starting in 2026. We’ll update this with details on each project before it starts.
Transport project
Water project
Existing project underway