Work is underway to clear slips on several roads in Banks Peninsula following the December 2021 storm event.
Heavy rain in December 2021 caused large slips, drop outs and scouring on several roads around Banks Peninsula. Our staff and contractors have been working to clear slips and repair roads.
Work will be ongoing on particular roads over the coming months. You can subscribe to our newsletter below. Newsletters will also be posted on this page.
Sign up to stay updated on the latest roading information following the December 2021 Banks Peninsula storm.
Scouring and road dropouts.
The remaining scouring repairs will begin in May.
These scouring repairs are expected to take several weeks to repair.
Fully open. Road users should take care when passing scouring on the road shoulder.
Various small slips, three road dropouts and flooding at the bottom of the road.
The road dropout repairs have been delayed and are expected to begin in June.
This will take 6 to 8 weeks to complete.
Fully open. Road users should take care when passing the dropouts on this road.
Various small slips, three road dropouts and flooding at the bottom of the road.
Repairing the road dropout, road metaling and culvert works.
The road metaling should be finished by the end of this week.
The dropout repair and culvert works will be completed in June.
Fully open. Road users should take care when passing the dropouts on this road.
Various full length slips, dropouts on the bottom half of the road, with a full road dropout approximately halfway down.
The culverts have all been installed at the main dropout.
Below the main dropout, work is ongoing. Following the completion of this work, the road will be re-metalled.
Work below the main drop out is likely to be completed in late June.
The road remains closed to all non-residents and landowners until repairs are complete along the entirety of Goughs Road.
Gated, with resident and farm only access
Various slips along the full length and one main road drop out halfway.
There has been no further work carried out at Hickory Bay.
Still need to repair the road dropouts and culverts.
Work repairing the road dropouts and the culverts will continue in mid-May. We expect this work to be finished in early June.
The road is now open to the public with long delays to be expected when works are occurring.
Due to the narrow road and the ongoing risk of rockfall, especially in rain events, signs have been installed at the start of the road to warn motorists.
Severe scouring and slips on Lavericks Ridge Road.
The final dropout repair has been competed. Crews have also finished upgrading the culverts.
More metal will need to be applied to the road before repairs are completed.
The metalling is expected to be completed in late May.
The road is now open to the public. People should take care until all dropouts are repaired and the road metal has been spread.
Various flooding debris, one large debris flow and one blocked culvert that caused damage to the road seal.
The small pavement repairs have been completed.
The completed small pavement repairs will be resealed.
The final reseal will be completed this week.
All remedial work on this road will be completed following the seal of the small pavement repairs.
Fully open.
Significant scouring, slips and dropouts. Significant damage to the second bridge.
Our contractors began working on the bridge repair.
No further works planned for this road.
We expect that all the work on the bridge will be finished by mid-June.
Fully open.
Scouring at the bridge and washouts.
Some scouring at the bridge and multiple washouts have been repaired.
Contractors have completed most stabilisation repairs.
There is one dropout that needs repair and sections of the road still require resealing.
Expected to be completed within the month.
Fully open.
Various small and large slips the full length from Fisherman's Bay Road, with a large dropout above Paua Bay Road and various slips.
The ford repairs are now complete.
Long Bay will also require further river protection works.
The road will also require re-metalling.
Our contractor plans to start re-metalling the road next week.
The river protection work will begin at the start of June.
Road is still closed at the Goughs Road intersection, with resident and farm only access.
Severe scouring and slips on the outer side of the harbour.
Metal build-up on the bottom end of the road along with a couple of culvert replacements.
Work is expected to be completed by the end of May.
Fully open.
Road dropout.
The dropout has been repaired.
Chipseal road surfacing repairs.
Work is expected to be completed within two months.
Fully open.
Read our most recent newsletters: