Christchurch Town Hall reopened to the public for the first time in eight years in February 2019.

The restoration of the Douglas Lilburn Auditorium, the Avon Room (the former Boaters Restaurant), Victoria and Limes Rooms was completed in February 2019 and the public got a chance to see inside for the first time(external link) during two open days.

Christchurch Symphony Orchestra (CSO), with Shapeshifter, were the first to perform in the newly restored Town Hall's Douglas Lilburn Auditorium on 1 March 2019.

The James Hay Theatre reopened in May 2019(external link), with the Celtic Tenors the first to take to the stage on 29 May.

With construction work still to be completed on the new Christchurch Symphony Orchestra (CSO) building, there is currently no public access to the building outside ticketed events. The CSO Centre will be completed later in 2019.

Town Hall interior

The Town Hall has been strengthened to 100 per cent of the new building standard and significantly refurbished, ensuring it is a modern, world-class facility that can be enjoyed for many years to come.

We have identified opportunities to bring the Town Hall up to modern standards as construction has progressed, while retaining its unique heritage features.

The purpose-built facility for the CSO gives the orchestra a permanent home in the Town Hall complex for the first time.

In May 2018, the Council approved $152.2 million in funding for the Town Hall plus the purpose-built CSO facility. On 19 December 2019, it approved additional funding of up to $15 million.

Town Hall timeline

November 2012

The Council considered a report outlining the damage and providing options on the future of the Town Hall.

The Council voted unanimously to repair the existing facility to 100 per cent of New Building Standard.

August 2013

Following overwhelming support from the public to restore the Town Hall as part of the 2012/13 Annual Plan process, the Council reconfirmed its commitment to restoring the facility to 100 per cent of New Building Standard on 29 August 2013.

June 2015

Christchurch City Council votes to fully repair and restore the earthquake-damaged Town Hall at a cost of $127.5 million.

Hawkins is appointed as the main contractor and site preparations begin.

The option of building a new 1500 seat auditorium and 600 seat theatre on a new site – as outlined in the Christchurch Central Recovery Plan – at a cost of $193.5 million was considered by the Council, but rejected.

November 2015

Work to strengthen the Town Hall’s badly damaged foundations begins.

January 2016

Approval is given to upgrade the Auditorium’s stage by installing stage lifts.

The decision is also taken to improve the Avon Room's (former Boaters restaurant) accessibility by making the floor all one level.

Mid 2016

Approval is given to add acoustics to the James Hay Theatre to improve the sound quality.

June 2016

As part of its 2016/17 Annual Plan process, the Council adjusts the budget for the Town Hall to take into account inflationary pressures. The adjustment takes the total approved budget to $133.1 million.

December 2016

A fly tower (or theatrical rigging system) is added to the scope of works for the James Hay Theatre.

May 2017

Retractable seating is approved for the James Hay Theatre.

July 2017

Agreement is given, in principle, for the Cambridge Room to be rebuilt as a purpose-built facility for the Christchurch Symphony Orchestra.

March 2018

Approval is given for additional security cameras to be installed in the Town Hall.

May 2018

Council approves additional budget for improvements to the Town Hall, bringing the total budget to $152.2 million.

February 2019

The first areas in the Town Hall, including the Douglas Lilburn uditorium, the foyer, the Avon Room (former function room), the Victoria and Limes Rooms, are complete. Public open days will run from 23-24 February.

March 2019

The first event, CSO with Shapeshifter, was held in the newly restored Town Hall on 1 March 2019.