Halswell Rd / Augustine Drive Intersection Improvements

What

To upgrade the existing intersection. Works to include new kerb and channel, full reconstruction of the existing carriageway and all associated drainage works and road marking. Works will also include the installation of new traffic signals, and upgrading the street lighting

Where

Halswell Rd (SH75) between Aidanfield Drive and Hendersons Rd

When

Works are due to start on the 22nd January 2018 and be completed by 30th June 2018

Why

The existing intersection at Halswell Rd and Augustine Drive is being upgraded to accommodate the anticipated increase in traffic volumes as a result of the new developments at Monsaraz Blvd and Nga Puna Wai Sports Hub

Contact

The contractor is Fulton Hogan phone 0800 275 342 between 12:00am- 12:00pm (Monday to Friday). Advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works

During the works traffic management will generally consist of:

  • Shoulder closures
  • Contra flow (Lane shifts) on Halswell Road
  • 30 kph speed restriction will be enforced through the works