Highfield - Services Extension along Mills Road

Update

What

We are extending new water and sewer pipes to cope with future growth.

Why

The Redwood area is growing and we need to provide underground services to cater for this growth.

Where

Along part of Prestons Road and then north along Mills Road.

When

Works are due to commence at the end of July 2019 and take approximately three months to complete.

Contact

The contractor is John Fillmore Contracting Limited. Phone03 343 1057 between 7.00am and 6.00pm or 027 522 0270 outside of these hours. Please advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • Work will commence on the north side of Prestons Road, near where new pipes were laid up to in 2018.
  • These will then be extended up the west side of Mills Road.