Eastman Wetland Basin

What

Constructing a bund which will form one side of the Eastman Wetland Basin and realigning Milns Drain around the basin.

Why

The Land Drainage Recovery Progamme is constructing this basin to reduce the risk of flooding in the Heathcote River due to earthquake effects. This basin is part of the Upper Heathcote Storage Scheme.

Where

332, 334 and 338 Sparks Road and 482A Cashmere Road.

When

Work will start 22 January 2019 for approximately 5 months.

Contact

The contractor is Grounds and Services Limited. Phone Darcy Arnold on 021-326-089 between 7:30am to 5pm Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • There will be some increase in traffic on Sparks Road from construction vehicles and deliveries to and from the site.

Takiuru ki ā mātou ratonga