What |
Replacing the watermains and submains. |
---|---|
Why |
The watermains have reached the end of their economic life and increased maintenance costs make replacement more economical. |
Where |
Along the entire length of Jocelyn Street. |
When |
Work will start late September and is expected to finish in December 2018. |
Contact |
The contractor is John Fillmore Contracting. Phone 027 522 0270 between 7am to 6pm, Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works. |
There may be times when vehicle access to your property is restricted. This will be temporary and our contractor will door knock beforehand so you can move your vehicle if necessary.
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Other projects
Learn more about our work.
ccc.govt.nz/works
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch