Brougham/Selwyn Streets - stormwater pipe replacement

What

We’re replacing brick barrel stormwater pipes at the intersection of Brougham and Selwyn Streets.

Why

The existing pipes have reached the end of their useful life and require replacement.

Where

Brougham Street, Selwyn Street and Somerset Crescent.

When

Work will start on 28 September 2020 and is expected to be completed by March 2021 (weather dependent).

Contact

The contractor is Downer NZ. Phone Marc Bos on 0800 026 420 between 7am to 5pm.

Details

  • The work will be carried out across different stages to reduce the traffic and access impact
  • Brougham Street will remain open at all times
  • Traffic management restrictions and detours will be in place (one-way closure and road closures) on Selwyn Street and Somerset Crescent. Please follow all temporary signage
  • All businesses located near the work area will remain open and signs will show how to access the shops and where to park
  • The work may result in increased dust, noise and vibrations. We will try to keep any disruption to a minimum
  • There may be times when vehicle access to properties is temporarily restricted. The contractor will contact residents beforehand to allow the movement of vehicles if necessary.

Stage one

The first stage of works will take about five weeks and involve installing new concrete pipes on Brougham Street (east side of the intersection) and on Somerset Crescent.

Stay updated

We’ll put newsletters out at times throughout the construction period. If you would like to subscribe please visit our webpage at ccc.govt.nz/brougham(external link) and subscribe to the newsletter.

Alternatively you can email broughamSW@ccc.govt.nz and ask to be added to the mailing list.