WW PS31 Barnett Capacity Improvement

What

Potholing for services cover measurement in the cross-over area presented in plan, extra 2 potholes - 30m from the pipes intersections, along the road, one on each side. TMP, GPR and Survey of marked up services and utilities, full reinstatement of surface. 1 lane closed

Why

Locate and identify gradients for the pipes built during SCIRT period to identify the high point, gradients and exact cover for the pipes in the cross-over area as per the plan below. Confirm pipes gradients with two more potholes 30m from this point, up and down the road.

Where

154 McCormacks Bay, Redcliffs, Christchurch

When

Wednesday 27th November 7.00am to 4.00pm

Contact

Contractor: CITY CARE - Barry Templeton – Senior Project manager M +64 27 704 5734 D 03 966 5429