Port Levy Wharf

What

Maintenance work is planned for Port Levy wharf. Three new piles will be driven.

Why

The wharf is kinked at present and is to be straightened through driving new piles.

Where

Port Levy Wharf

When

Work will start Thursday 17th October 2019 to Friday 1st November 2019.

Contact

The contractor is Maintenance Management Services. Phone Brent McKay 027 433 2284 between 8.00am to 5.00pm from Monday to Friday. Advise us if you have specific wharf access requirements during this period.

  • These skewed piles will be replaced and an attempt to straighten the wharf will be made.

 

 

 

 

 

 

 

 

  • A dive inspection indicated pile 13A is wormed out at the seabed. It will be replaced.