What |
The remediation works to the retaining wall at 1 Cressy Terrace consists of soil nail anchoring, drainage and minor landscape works. |
---|---|
Why |
The existing retaining wall requires remediation works as a result of earthquake damage. |
Where |
1 Cressy Terrace, Lyttelton |
When |
Construction is due to commence the last week of July 2019, with completion early November 2019. |
Contact |
The contractor is Rock Control Ltd. Phone Tom Adams 027-568-1012 between Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works. |
The work is expected to commence the last week of July 2019 and be completed early November 2019 weather dependant.
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins
Please put your bins out as usual before 6am on your collection day. Our crew will move and return them if needed.
Other projects
Learn more about our work.
ccc.govt.nz/works
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch
Request, report and pay for Council services.
Apply for building and resource consents.
Manage your library borrowing.
Receive your rates invoice by email.
Take full control of your Rec and Sport membership.
List your events on What’s On Christchurch