Rhonda Street Wastewater Renewal

What

Replacing the wastewater main and laterals.

Why

The wastewater mains have reached the end of their economic life and increased maintenance costs make replacement more economical.

Where

Rhonda Street from Buckleys Road to number 51 Rhonda Street.

When

The Contractor will be establishing on site on 15 July 2019 and should be completed by 30 August 2019.

Contact

The contractor is City Care Limited. Phone 027 248 0337 between 7.00am and 6.00pm Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • There may be times when vehicle access to your property is restricted.
  • This is temporary and our Contractor will door knock beforehand so you can move your vehicle, if necessary.