Highfield - upcoming work during July School Holidays

Update

What

We are working on new pipe connections to the existing sewer.

Why

The Redwood area is growing and we need to provide underground services to cater for this growth.

Where

At the intersection of Main North Road and Prestons Road.

When

Works will commence during the July school holidays. See below for details.

Contact

The contractor is John Fillmore Contracting Ltd. Phone 03 343 1057 between 7.00am and 6.00pm or 027 522 0270 outside of these hours. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • Following on from work undertaken just after Easter, the second stage of this work is due to occur during the July school holidays, commencing Friday 5 July 2019.
  • None of this is planned to require night time work, however signage will remain in place 24 hours a day.
  • Commencing Friday 5 July 2019, one of the southbound lanes on Main North Road will be closed and remain closed until 7.00am on Monday 22 July 2019.  During this time, a deep manhole will be built over the trunk sewer line in Main North Road.
  • After the manhole is built, a short trench will be extended east along Prestons Road back to where trenching work stopped in November 2018.  This work will commence on 22 July 2019 and take approximately three (3) weeks.
  • During this time, a one way system for eastbound traffic on Prestons Road will be in place.
  • Westbound traffic will again be detoured via Daniels Road.