Le Bons Bay Public Toilet Disposal Upgrade

What

We are upgrading the disposal method for wastewater from this public toilet.

Why

To provide an improved disposal solution.

Where

By the current location of the public toilet at Le Bons Bay.

When

Works commence at the beginning of April and take approximately three weeks.

Contact

The contractor is John Fillmore Contracting phone 03 343 1057 between 7am- 6pm (Monday to Friday), or 027 522 0270 outside of these hours. Please advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works..

The works will involve trenching a new pipe to new dispersal fields located to the south